Method Statement for Brickwork
1.0 Scope & Objectives
- This Method Statement details the standardized construction procedure for executing quality Brickwork.
3.0 References
- Project Technical Specifications
- Approved Civil Drawings
- Indian Standard (IS) Codes:
- IS 1077:1992 – Common burnt clay building bricks – Specification
- IS 2117:1991 – Guide for manufacture of hand-made common burnt clay building bricks
- IS 2119:1980 – Code of practice for construction of brick-cum-concrete composite floor/roof
- IS 2180:1988 – Specification for heavy duty burnt clay building bricks
- IS 2212:1991 – Code of practice for brick works
- IS 2222:1991 – Specification for burnt clay perforated building bricks
- IS 2691:1988 – Specification for burnt clay facing bricks
- IS 3068:1986 – Specification for broken brick coarse aggregates for lime concrete
- IS 3182:1986 – Specification for broken brick fine aggregates for lime mortar
- IS 3495 (Parts 1–4):1992 – Methods of tests of burnt clay building bricks (Compressive strength, Water absorption, Efflorescence, Warpage)
- IS 3952:1988 – Specification for burnt clay hollow bricks for walls/partitions
- IS 4139:1989 – Specification for calcium silicate bricks
- IS 4860:1968 – Specification for acid-resistant bricks
- IS 4885:1988 – Specification for sewer bricks
- IS 5454:1978 – Methods of sampling of clay building bricks
- IS 5766:1970 – Code of practice for laying burnt clay brick flooring
- IS 5779:1986 – Specification for burnt clay soling bricks
- IS 6165:1992 – Dimensions for special shapes of clay bricks
- IS 12894:2002 – Specification for pulverized fuel ash lime bricks
4.0 Definitions & Terminology
Abbreviations
- MS: Method Statement
- QCP: Quality Control Procedure
- ITP: Inspection & Test Plan
Brickwork Terminology
- Bull Header: A rowlock brick laid with its longest dimension perpendicular to the face of the wall.
- Bull Stretcher: A rowlock brick laid with its longest dimension parallel to the face of the wall.
- Course: A continuous horizontal row of masonry units bonded together.
- Header: A brick laid flat with its longest dimension perpendicular to the face of the wall to tie wythes together.
- Rowlock: A brick laid on its face or edge.
- Soldier: A brick laid on its end so its longest dimension is parallel to the vertical axis of the wall.
- Stretcher: A brick laid flat with its longest dimension parallel to the face of the wall.
- Wythe: A continuous vertical section/thickness of masonry (4" or greater).
Types of Masonry Bonds
- Running Bond: Simplest pattern consisting only of stretchers; requires reinforcing ties.
- Common (American) Bond: Variation of running bond with courses of full-length headers at regular intervals.
- Flemish Bond: Alternating stretchers and headers in each course, centered over the course below.
- English Bond: Alternating courses of stretchers and headers with aligned vertical joints for stretchers.
- English Cross (Dutch) Bond: Variation of English bond where vertical joints in alternate stretcher courses are offset.
- Stack (Block) Bond: Decorative pattern with all vertical joints aligned; non-structural unless reinforced.
5.0 Health & Safety Hazards
Specific safety measures must be followed as applicable on-site. All site personnel must strictly adhere to the provisions established in the main Project Safety Plan.
6.0 Responsibilities
| Role | Key Responsibilities |
|---|---|
| Project Engineer | Ensures brickwork conforms to specifications/drawings, manages schedules/equipment, coordinates with Clients/Consultants, and enforces safety and quality compliance. |
| Site Engineer | Distributes tasks, monitors daily work progress against schedules, coordinates with QA/Safety/Surveyors, and delivers revised site info to foremen. |
| QA Engineer | Ensures compliance with QCP/specifications, inspects finished work prior to client approval, and maintains inspection and testing records. |
| Safety Engineer | Implements the HSE plan, conducts site risk assessments, delivers safety training, prevents hazards, and maintains site cleanliness. |
| Foreman | Manages daily labor allocation, provides daily site progress reports, assists the site surveyor, and directly executes quality/safety directives. |
| Surveyor | Establishes benchmarks, marks setting-out lines/levels, and conducts periodic checks to verify horizontal and vertical alignment. |
7.0 Procedure / Method to be Employed
7.1 Site Selection & Preparation
- Select site locations on firm ground with effective drainage, avoiding proximity to large tree roots.
- Construct concrete footers or foundations and allow a minimum curing period of 2 days before laying bricks.
- Stack bricks systematically across the job site and pre-dampen/hose them down a few hours prior to laying to prevent absorption of mortar water.
- Snap chalk guidelines from foundation edges to maintain true alignment.
7.2 Mortar Preparation & Brick Laying
- Mix mortar to a smooth, plastic-like consistency.
- Conduct a dry run by laying stretchers along chalk lines (allowing a ½" head joint) to verify alignment before applying mortar.
- Apply mortar roughly 1" thick, 1 brick wide, and 3 to 4 bricks long, furrowing slightly with the tip of the trowel.
- Lay the first course firmly into place; check alignment, height, and level using a spirit level. Tap gently to adjust—never pull set bricks.
- Construct end and corner leads (5 courses high) utilizing cut half/quarter bricks for bond staggering. Verify square corners using the 3-4-5 rule or a carpenter's square.
- String a mason's line 1/16" off the brick face between leads and complete the interior courses working toward the center.
7.3 Finishing Mortar Joints
- Concave & V-Joints: Preferred for structural durability and high resistance to water penetration.
- Weathered Joints: Highly watertight and strong.
- Flush Joints: Simple, flat finish cut off by trowel (moderate strength/weather resistance).
- Raked / Struck / Extruded: Decorative; not recommended in high-rainfall or freezing climates.
7.4 Pillars, Posts & Edging
- Pillars: Cast firm concrete footings. Install vertical reinforcement steel or electrical conduits prior to pouring, check vertical plumb constantly, and top with sloped concrete or stone caps to shed water.
- Brick Edging: Excavate a trench (4" deep, 8" wide), tamp soil smooth, lay mortar mix, set bricks firmly, and trim excess mortar.
8.0 Materials & Equipment Requirements
- Bricks & Mortar/Mason Mix
- Chalk Line & Mason's Line
- Line Blocks & Mortarboard
- Water Hose & Wheelbarrow
- Brick Trowel & Concave Jointer
- Spirit Level & Carpenter's Square
- Measuring Tape
- Brick Set & Mason's Hammer
- Safety Goggles / Personal Protective Equipment
9.0 Health & Safety Provisions
- Erect safety barriers, warning signs, and warning tape around active construction zones.
- Provide working platforms and edge protection when brickwork is carried out at elevated heights.
- Enforce additional safety checks during formwork or platform stripping operations.
10.0 Quality Control Approvals
Prior to commencing work, the following documents must be submitted and approved:
- Quality Control Procedure (QCP) for Brickwork
- Inspection & Test Plan (ITP) for Brickwork
- Project Field Quality Plan
- Brickwork Checklist Forms
11.0 Supporting Documentation
- Contract Specifications & Approved Drawings
- QCP and ITP for Brickwork
- Method Statement (MS) for Brickwork
- Project Quality Plan & Project HSE Plan
12.0 Distribution List
Issued to: Management Representative | Project Manager | Project Engineer | Site Engineer | HSE Engineer | QA/QC Engineer