Method Statement for Plain Cement Concrete (PCC) Works

1.0 Revision Status

Revision Number Date Originator Reviewed Approved Description of Re-submittal
           
           
           

2.0 Scope & Objectives

  • This Method Statement details the complete procedure for Plain Cement Concrete (PCC) works[cite: 1].
  • PCC with an aggregate size of 40 mm is utilized as a bed/levelling layer for foundations and flooring[cite: 1].
  • PCC with an aggregate size of 20 mm is utilized for window sills, coping, and damp-proof courses (plinth concrete) incorporating waterproofing compounds[cite: 1].

3.0 Reference

  • Project Technical Specifications[cite: 1]
  • Contract Drawings[cite: 1]
  • IS 456:2000 – Plain and Reinforced Concrete: Code of Practice[cite: 1]
  • IS 6461 (Part 7): 1973 – Code of symbols, terms and definitions relating to concrete: Part 7 Mixing, laying, compaction, curing and other constructional aspects[cite: 1]
  • IS 4845 – Definitions and terminology relating to hydraulic cement[cite: 1]

4.0 Definitions & Abbreviations

  • MS: Method Statement[cite: 1]
  • QCP: Quality Control Procedure[cite: 1]
  • ITP: Inspection & Test Plan[cite: 1]

5.0 Health & Safety Hazards

Specific safety measures must be followed as applicable[cite: 1]. All mandatory health, safety, and environmental measures are detailed separately in the Project Safety Plan[cite: 1].

6.0 Responsibilities

6.1 Project Engineer

  • Ensure all PCC works are executed strictly in accordance with approved specifications and drawings[cite: 1].
  • Verify that ongoing activities adhere to the planned construction program and that all required equipment is on site and in good operational condition[cite: 1].
  • Coordinate with the Client/Consultant, Project Manager, Site Engineer, Safety Engineer, and Surveyor for safe, smooth execution[cite: 1].
  • Enforce safety measures and quality control in conjunction with the Safety and QA/QC Engineers following the project HSE and Quality Plans[cite: 1].

6.2 Site Engineer

  • Directly supervise PCC operations as per project specifications and construction drawings[cite: 1].
  • Distribute daily site responsibilities and technical details to the construction execution team[cite: 1].
  • Monitor daily work progress against the project schedule and report updates to the Project Engineer/Manager[cite: 1].
  • Coordinate with Safety personnel to maintain safe working practices at all times[cite: 1].
  • Coordinate with QA/QC engineers to initiate timely sampling, testing, and final inspections[cite: 1].
  • Ensure maximum productivity from deployed labor and machinery, cross-checking outputs against daily foreman reports[cite: 1].
  • Communicate updated drawing revisions to foremen promptly[cite: 1].
  • Coordinate with the surveyor to verify lines, levels, and structural alignments[cite: 1].

6.3 QA Engineer

  • Verify that all ongoing and completed PCC works comply with project specifications and quality procedures[cite: 1].
  • Perform physical inspections of finished works prior to submitting requests for Client/Consultant approval[cite: 1].
  • Maintain structured inspection and concrete test records for future reference[cite: 1].

6.4 Safety Engineer

  • Enforce site implementation of all safety measures outlined in the HSE plan[cite: 1].
  • Inspect active site areas to verify safety adequacy and conduct toolbox talks to prevent site incidents[cite: 1].
  • Maintain clean and tidy work areas across all PCC activity zones[cite: 1].

6.5 Foreman

  • Manage daily labor and equipment distribution in coordination with the Site Engineer[cite: 1].
  • Submit daily output reports and assist in short-term work planning[cite: 1].
  • Coordinate directly with surveyors for setting out and reference marking[cite: 1].
  • Implement all safety and quality control requirements passed down by project engineers[cite: 1].
  • Report any site delays or unforeseen site conditions to the Site Engineer immediately[cite: 1].

6.6 Surveyor

  • Establish benchmarks from verified control points and provide all line, layout, and level markings[cite: 1].
  • Maintain all survey data and perform periodic level checks on ongoing PCC pours[cite: 1].

7.0 Procedure / Method to be Employed

7.1 Site Preparation & Layout Check

  • Verify layout, line, levels, and plan dimensions with the survey team prior to placing concrete[cite: 1].

7.2 Concrete Mix & Proportioning

  • Nominal Mix: Use 1:2:4 (Cement : Sand : Coarse Aggregate) by volume when specified[cite: 1].
  • Compressive Strength: Standard 1:2:4 nominal mix concrete must achieve a minimum 7-day compressive strength of 140 kg/cm²[cite: 1].

7.3 Concrete Mixing

  • Hand Mixing: Permitted only on a watertight masonry platform or heavy-duty sheet iron tray[cite: 1].
  • Machine / Batch Mixing: Load coarse aggregates, sand, and cement into the mixer drum in correct proportions to obtain a uniform distribution[cite: 1].

7.4 Slump Control

  • Conduct standard slump tests regularly to control water additions and maintain concrete consistency[cite: 1].
  • Maintain a slump range between 7.5 cm and 10 cm for general building works[cite: 1].

7.5 Formwork & Shuttering

  • Provide sturdy shuttering and centering to support and confine concrete to design dimensions[cite: 1].
  • Apply approved shuttering oil on inner faces to prevent concrete sticking upon stripping[cite: 1].

7.6 Concrete Placement & Compaction

  • Deposit concrete gently into place (do not drop from height or throw) in uniform layers not exceeding 15 cm in depth[cite: 1].
  • Compact thoroughly using steel rods, wooden tampers, or mechanical immersion/screed vibrators to eliminate voids and achieve maximum density[cite: 1].
  • Ram and finish the top concrete surface smooth to correct design levels[cite: 1].

7.7 Curing

  • Initial curing must begin within ~2 hours of placement as soon as the surface hardens[cite: 1].
  • Keep surfaces continuously damp by covering with wet gunny bags or wet sand for at least 24 hours[cite: 1].

8.0 Material Requirements

Coarse Aggregates

  • Must consist of inert, clean, dense, hard, durable, non-absorbent, broken stone (granite or equivalent)[cite: 1].
  • Free from dirt, clay, organic matter, and dust[cite: 1].
  • Graded 20 mm nominal size and below, completely retained on a 5 mm square mesh, with voids not exceeding 42%[cite: 1].

Fine Aggregates (Sand)

  • Clean coarse sand with hard, sharp, angular grains passing through a 5 mm square mesh[cite: 1].
  • Free from silt, clay, organic impurities, and salts. Sea sand is strictly prohibited.[cite: 1]

Cement

  • Fresh Portland cement conforming to ISI standards with proper strength and fineness[cite: 1].

Water

  • Clean, fresh, free from acids, alkalis, oils, or organic materials, and suitable for drinking purposes[cite: 1].

9.0 Equipment Requirements

Auto Level Instrument & Staff[cite: 1]
Transit Mixer / Concrete Mixer[cite: 1]
Wooden & Steel Rammers[cite: 1]
Plate Compactor[cite: 1]
Internal Needle Vibrators[cite: 1]
External Form Vibrators[cite: 1]
Concrete Placer & Spreaders[cite: 1]
Finishing Trowels[cite: 1]
Concrete Edgers & Groovers[cite: 1]
Concrete Stamps & Rollers[cite: 1]
Carpentry & Shuttering Tools[cite: 1]

10.0 Health & Safety Provisions

  • High importance is assigned to jobsite safety to ensure safe execution of all PCC activities[cite: 1].
  • Erect physical barriers, safety signboards, and warning tape around foundation pits at least 1 meter away from excavation edges[cite: 1].
  • For deep excavation pits subject to ground collapse risks, ensure earth sides are properly sloped back, stepped, or shored prior to labor entry[cite: 1].

11.0 Quality Control Approvals

The following technical documents must be formally approved prior to starting PCC works[cite: 1]:

  • Quality Control Procedure (QCP) for PCC Works[cite: 1]
  • Inspection & Test Plan (ITP) for PCC Works[cite: 1]
  • Project Field Quality Plan[cite: 1]
  • Inspection Checksheets for PCC Works[cite: 1]

12.0 Supporting Documentation

  • Contract Specifications and GFC Drawings[cite: 1]
  • QCP for PCC Works[cite: 1]
  • ITP for PCC Works[cite: 1]
  • Method Statement (MS) for Earthworks[cite: 1]
  • Project Quality Plan[cite: 1]
  • Project HSE Plan[cite: 1]

13.0 Distribution List

Copies issued for review, compliance, and field execution[cite: 1]:

  • Management Representative[cite: 1]
  • Project Manager[cite: 1]
  • Project Engineer[cite: 1]
  • Site Engineer[cite: 1]
  • HSE Engineer[cite: 1]
  • QA/QC Engineer[cite: 1]
Yogendra Gopal Borse

Yogendra Gopal Borse

Civil Engineer | Assistant Engineer Grade-I, Maharashtra PWD

B.Tech (Civil) from VJTI Mumbai. Experienced in bridge design, road works, estimation, project monitoring and digital engineering tools. Creator of YogiPWD – practical technical resources for civil engineers.

Read full About →