YogiPWD

STP Load Calculation for Residential High-Rise Building

STP Load Calculation for Residential High-Rise Building – Detailed Guide with Solved Example

STP Load Calculation for Residential High-Rise Building

Solved Example with Formulas, Design Basis & Practical Guidance

Based on CPHEEO Manual, NBC 2016, CPCB/SPCB Norms & IS 18997:2024

1. Introduction

A Sewage Treatment Plant (STP) is essential for any residential high-rise building to treat wastewater generated from toilets, kitchens, bathrooms and utility areas before reuse or safe disposal. Proper load calculation ensures the plant is neither under-designed (leading to poor performance) nor over-sized (wasting capital and operating cost).

This article presents a complete, step-by-step worked example for a typical 500-flat residential high-rise project, covering hydraulic design, pollution load, capacity selection, unit sizing and treated water reuse.

Golden Rule of STP Design:
Average Daily Flow (ADF) is used for biological process design and overall capacity selection.
Peak Flow is used only for hydraulic components (inlet works, screens, channels, pumps, pipes).

2. Project Details (Assumed)

ParameterValue
Type of BuildingResidential High-Rise
Number of Flats500 Nos.
Average Occupancy4 Persons / Flat
Total Population500 × 4 = 2,000 Persons
Water Supply Basis135 LPCD (Litres Per Capita per Day) – Residential
Sewage Generation80% of Water Supply (as per CPHEEO)
Design StandardsCPHEEO Manual on Sewerage & Sewage Treatment (2013), NBC 2016 Part 9, CPCB/SPCB Norms, IS 18997:2024

3. Water Demand Calculation

1 Daily Water Demand
Daily Water Demand = Population × LPCD
= 2,000 × 135
= 270,000 L/day = 270 KLD

LPCD = Litres Per Capita per Day

4. Sewage Generation (Domestic)

2 Average Sewage Flow (ADF)
Sewage Generation = 80% of Water Supply
= 270 KLD × 0.80
= 216 KLD
Average Daily Flow (ADF) = 216 KLD

This is the most important number used for process design of the biological reactor, secondary clarifier and overall plant capacity.

Reference: As per CPHEEO Manual, domestic sewage is typically taken as 80% of water supply. IS 18997:2024 also recommends 108 LPCD wastewater generation for residential buildings (which is 80% of 135 LPCD).

5. Average Sewage Flow – Hourly Conversion

3
Average Hourly Flow = 216,000 L/day ÷ 24
= 9,000 L/hour = 9.0 m³/hr

6. Peak Sewage Flow (Hydraulic Design)

Peak Factor depends on contributing population as per CPHEEO Manual:

Population (Contributing)Peak Factor (PF)
Up to 20,0003.0
20,001 – 50,0002.5
50,001 – 5,00,0002.0
Above 5,00,0001.5
4 Calculation for our project (Population = 2,000)
Peak Factor (PF) = 3.0

Peak Sewage Flow = ADF × Peak Factor
= 216 KLD × 3.0
= 648 KLD
Peak Flow = 648 KLD = 27 m³/hr = 7.5 L/sec
Important Note:
• Peak Flow (648 KLD) is used only for hydraulic design of inlet works, bar screens, grit chambers, channels, pumps and pipelines.
• STP biological process capacity is always designed on Average Daily Flow (216 KLD).

7. STP Capacity Selection

While the average sewage generation is 216 KLD, practical capacity selection considers:

  • Future load (staff, visitors, club house, commercial areas)
  • Safety margin (10–20%)
  • Possible increase in occupancy or water use
Proposed STP Capacity = 250 KLD (Preliminary Selection)

This provides approximately 15–16% extra margin over the calculated ADF of 216 KLD.

8. Pollution Load Calculation

Assumed characteristics for domestic sewage (typical values):

Parameter Unit Typical Value Load Calculation (216 KLD) Load (kg/day)
BOD mg/L 250 216,000 L/day × 250 / 1000 54.0
COD mg/L 500 216,000 × 500 / 1000 108.0
TSS mg/L 200 216,000 × 200 / 1000 43.2
Oil & Grease mg/L 20 216,000 × 20 / 1000 4.32
General Formula:
Load (kg/day) = Flow (L/day) × Concentration (mg/L) / 1000

Design of the biological reactor is primarily based on BOD Load = 54.0 kg/day.

9. Flow Summary

Description Qty (KLD) In m³/hr Remarks
Average Daily Flow (ADF) 216 9.0 For Process Design
Peak Hydraulic Flow (PF = 3.0) 648 27.0 For Inlet works, Pumps, Channels
Peak Discharge 7.5 L/sec For Hydraulic Components
Proposed STP Capacity 250 10.4 Preliminary Selection

10. Factors to Consider Before Final STP Capacity

  • Actual water consumption pattern (metered data preferred)
  • Flat occupancy variation (weekdays vs weekends)
  • Common area usage (landscaping, clubhouse, swimming pool backwash)
  • Staff / Kitchen / Restaurant / Commercial areas (if any)
  • Future expansion (10% to 20% additional capacity)
  • Reuse requirement of treated water
  • Local SPCB norms and discharge standards
  • Quality of influent water (low / high strength sewage)
  • Availability of space and power
  • O&M strategy and skilled manpower availability
Always select STP capacity based on engineering judgement with adequate safety margin, but avoid over-sizing.

11. Design Basis Summary

ItemBasisValue / Assumption
PopulationFlats × Occupancy500 × 4 = 2,000 Persons
Water SupplyAs per Project135 LPCD (Residential)
Sewage GenerationAs per CPHEEO80% of Water Supply
Average Sewage FlowCalculation216 KLD (9.0 m³/hr)
Peak FactorCPHEEO Manual3.0 (for Pop. up to 20,000)
Peak Sewage FlowADF × PF648 KLD (27 m³/hr)
Peak DischargeConversion7.5 L/sec
Proposed STP CapacitySelection250 KLD

12. Typical STP Process Flow Diagram

A modern residential high-rise STP typically follows this treatment train:

  1. Bar Screen (Channel) – Removes large solids (rags, plastics, sticks)
  2. Grit Chamber – Removes grit, sand and small stones
  3. Equalization Tank – Balances flow & load; homogenizes sewage
  4. Biological Treatment (SBR / MBBR / MBR) – Microorganisms break down organic matter (BOD, COD, TSS reduction)
  5. Secondary Clarifier – Settles biomass (sludge); clarified water overflows
  6. Tertiary Treatment (Filter) – Removes fine suspended solids and residual organics
  7. Disinfection (UV / Chlorine) – Kills pathogenic microorganisms
  8. Treated Water Tank – Stores treated water for reuse or final disposal

Sludge Line: Secondary Clarifier → Sludge Holding Tank → (Optional Thickener) → Sludge Dewatering (Belt Filter Press) → Dry Cake / Biosolids Disposal

Typical Removal Efficiency

Parameter% Removal (Typical)
BOD90 – 95 %
COD85 – 95 %
TSS90 – 95 %
Oil & Grease80 – 90 %
Pathogens> 99 %

13. Indicative Unit Sizing (for 250 KLD STP)

Unit Design Criteria Qty / Size (Approx.) Remarks
Bar Screen Clear bar opening 20–40 mm Manual / Mech. Channel width \~450 mm
Grit Chamber Detention Time 30–45 sec Size: 1.0 m (L) × 1.0 m (W) × 2.0 m (SWD)
Equalization Tank Detention Time 6–8 hr Volume ≈ 250 × 8/24 ≈ 83 m³ (Say 85 m³) With submersible mixers
Biological Reactor SBR: 4–6 cycles/day
MBBR: 30–40% Media
Volume: 250–300 m³ Based on technology provider
Secondary Clarifier
(if MBBR system)
Surface Loading 20–25 m³/m²/day Dia.: 8.0 m
SWD: 3.0 m
Central Drive / Rake
Tertiary Filter Filtration Rate 8–10 m³/m²/hr Dual Media Filter Sand + Gravel Filter
Disinfection Chlorine Contact Time 20–30 min Contact Tank Volume ≈ 250 × 30/(24×60) ≈ 5.2 m³ Provide baffle arrangement
Sludge Drying Bed
(if used)
Loading 30–50 kg/m² Area: 15–20 m² As per sludge quantity
Note: Actual sizing shall be as per detailed design and technology provider data.

14. Treated Water Reuse Calculation

Treated Water Available ≈ 216 KLD (Average)

Assumed Reuse Requirement:

  • Gardening / Landscaping → 120 KLD
  • Flushing (Common area) → 40 KLD
  • DG Set / Utility / Others → 20 KLD
Total Reuse = 180 KLD
Balance 36 KLD can be kept as buffer / surplus for future demand or discharge (as per norms).

15. Discharge Norms (Typical – As per CPCB / SPCB)

ParameterUnitPermissible Limit*
BODmg/L≤ 10
CODmg/L≤ 50
TSSmg/L≤ 20
Oil & Greasemg/L≤ 10
pH6.5 – 9.0
Total ColiformMPN/100 mL< 230

* As per CPCB / SPCB norms for inland surface water discharge (may vary as per local authority).

16. Pumps & Blowers (Indicative for 250 KLD)

A) Sewage Pump (Peak Flow 27 m³/hr)

  • Duty: 27 m³/hr at 12 m head
  • Quantity: 2 Working + 1 Standby
  • Type: Submersible / Dry well pump

B) Treated Water Pump

  • Duty: 12 m³/hr at 20 m head
  • Quantity: 2 Working + 1 Standby

C) Blowers (For Aeration in SBR / MBBR)

  • Air Demand: 0.4 – 0.6 m³/min per 100 KLD
    For 250 KLD → 1.0 – 1.5 m³/min
  • Quantity: 2 Working + 1 Standby
  • Type: Roots Blower
Selection shall be as per process requirements, head losses and technology provider data.

17. O&M Considerations

  • Ensure regular cleaning of screens and grit chamber
  • Monitor DO, MLSS (if applicable), pH and sludge volume
  • Check chemical dosing system and chlorine residual regularly
  • Ensure blower, pump and mixer preventive maintenance
  • Maintain log book for operating parameters and maintenance
  • Provide skilled operator and proper training

18. Key Points to Remember

  • Average Sewage Flow (ADF) is used for STP process design.
  • Peak Flow is used for hydraulic design of inlet works, screens, channels and pumps.
  • Proper screening, equalization and aeration are essential for efficient STP performance.
  • Always provide 10–20% safety margin but avoid excessive over-sizing.
  • Final design must comply with NBC, CPHEEO, SPCB/CPCB norms and technology provider recommendations.

19. References

  • CPHEEO Manual on Sewerage and Sewage Treatment Systems (2013)
  • National Building Code (NBC) 2016 – Part 9, Section 2 – Sanitation, Drainage & STP
  • CPCB / SPCB Guidelines for STP and Treated Water Reuse
  • IS 18997:2024 – Sewage Treatment Systems – Code of Practice
Disclaimer: This calculation is for preliminary estimation and planning purposes only. Final design shall be carried out by a qualified STP technology provider / consultant considering actual site conditions, local regulations and selected treatment technology.

Prepared for educational & reference purposes based on standard Indian design practices

Post a Comment

0 Comments