Portal Support in Himalayan Tunnelling – Rock Bolts, Shotcrete, Forepoling & Slope Stabilization

🏔️ Portal Support in Himalayan Tunnelling

Rock Bolts • Shotcrete • Forepoling • Steel Ribs • Drainage • Slope Stabilization • Monitoring

Himalayan Geology Tunnel Portals NATM RMR / Q-System Slope Stability

A practical engineering guide for understanding, designing and constructing safe tunnel portals in steep, weathered, fractured and water-bearing Himalayan terrain.

Engineering Disclaimer:
This article is intended for engineering education, preliminary understanding, DPR discussions and site-engineering reference. The support dimensions, rock-bolt spacing, shotcrete thickness and stability values shown in the worked example are illustrative only. Final support must be established from site-specific geological investigation, rock-mass classification, groundwater, slope stability analysis, seismic conditions, excavation methodology, instrumentation and approved design.

1. Introduction

A tunnel portal is the transition zone between the open hill slope and the underground excavation. Although the tunnel itself may be located in competent rock, the first few metres or tens of metres near the portal can contain highly weathered rock, colluvium, loose debris, fractured rock, soil-rock interfaces and uncontrolled groundwater.

This makes the portal one of the most vulnerable portions of a Himalayan tunnel project.

The objective of portal support is not merely to prevent a rockfall. A properly designed portal system must control:

⛰️ Slope Stability

Prevent sliding, toppling, wedge failure, ravelling and erosion of the approach cut.

🪨 Rock-Mass Stability

Prevent loosening and progressive failure around the tunnel opening.

💧 Water

Control rainfall runoff, seepage, pore pressure and concentrated water flow.

🚧 Construction Safety

Maintain adequate stand-up time during excavation and support installation.

2. Why Tunnel Portals Are Critical

The underground tunnel is normally surrounded by three-dimensional confinement. At a portal, that confinement is interrupted because one side of the excavation is open to the atmosphere.

Consequently, the portal zone can experience:

  • Reduced confinement
  • Wedge and block failures
  • Weathering and deterioration
  • Rainfall-induced erosion
  • Groundwater inflow
  • Unstable cut slopes
  • Rockfall from the crown
  • Face instability during initial excavation
  • Seismic deformation
Steep Himalayan slope Weathered / fractured zone Rock bolts Shotcrete / ribs Surface drainage Tunnel
Figure 1 – Conceptual tunnel portal showing slope, weathered zone, primary support and drainage.

3. Himalayan Geological Challenges

Himalayan tunnel projects frequently encounter rapid changes in geological conditions over short distances. A support class that is suitable for one chainage may become inadequate a few metres away.

Condition Typical Problem Engineering Response
Highly weathered rock Low stand-up time and ravelling Immediate shotcrete, bolts, mesh and controlled excavation
Shale / slate / phyllite Slaking, foliation-controlled failure Orientation-based bolting, shotcrete, ribs and drainage
Loose colluvium Flow/sliding into portal excavation Benching, retaining structures, canopy/forepoling
Fault/shear zone Gouge, large blocks and deformation Systematic anchors, spiling, steel ribs and controlled excavation
High groundwater Softening, erosion and hydrostatic pressure Drainage, probe drilling, grouting/sealing where appropriate
Heavy rainfall Surface erosion and infiltration Catch drains, lined drains and rapid runoff disposal
Seismic activity Dynamic instability Ductile support, reinforcement and monitoring

4. Geotechnical Investigation Before Portal Excavation

Portal support should begin with investigation rather than excavation. A tunnel portal is a three-dimensional geotechnical problem involving both the slope and underground opening.

4.1 Minimum investigation components

  • Detailed geological mapping
  • Engineering geological cross-sections
  • Rock-core drilling where required
  • RQD determination
  • Joint orientation survey
  • Joint spacing and persistence
  • Joint roughness and infilling
  • Groundwater/seepage mapping
  • Laboratory UCS and other relevant rock tests
  • Rock-mass classification
  • Slope stability assessment
  • Seismic hazard assessment
  • Existing landslide/debris-flow investigation
  • Drone/topographic survey where useful
  • Probe drilling during excavation

4.2 Critical geological questions

  1. Is the tunnel portal located on intact bedrock or on thick overburden?
  2. Does the foliation dip toward or away from the portal?
  3. Are there joints daylighting toward the cut slope?
  4. Is there a fault or shear zone crossing the portal?
  5. Is groundwater pressure likely to develop?
  6. Can rainfall enter the tunnel through the portal cut?
  7. Is there an old landslide or debris-flow channel?
  8. What is the expected stand-up time after excavation?

5. RMR and Q Rock-Mass Classification

Rock-mass classification is useful for converting geological observations into an engineering description of rock quality. ITA explains that rock-mass systems such as RQD, RMR and Q were developed because intact laboratory rock properties alone do not represent the behaviour of fractured rock masses.

5.1 RMR concept

The Rock Mass Rating system considers parameters such as:

  • Intact rock strength
  • RQD
  • Discontinuity spacing
  • Discontinuity condition
  • Groundwater
  • Joint orientation adjustment

The general concept is:

\[ RMR = \sum R_i + R_{\text{orientation}} \]

The actual rating must be determined using the applicable edition of the relevant standard/guideline and site observations.

5.2 Q-system

A widely used expression for the Q-system is:

\[ Q = \left(\frac{RQD}{J_n}\right) \left(\frac{J_r}{J_a}\right) \left(\frac{J_w}{SRF}\right) \]

where:

Parameter Meaning
RQD Rock Quality Designation
Jn Joint-set number
Jr Joint roughness number
Ja Joint alteration number
Jw Joint water reduction factor
SRF Stress Reduction Factor

The Q-value is therefore not merely a rock-strength number. It reflects block size, joint characteristics, groundwater and stress conditions.

6. Portal Support Philosophy

A robust portal system normally uses several support mechanisms working together rather than relying on one component.

1. Surface stabilization

Benching, retaining walls, gabions, shotcrete and surface anchors.

2. Rock reinforcement

Rock bolts, anchors and mesh tie potentially unstable blocks to the stable rock mass.

3. Surface confinement

Shotcrete seals the exposed rock and helps prevent ravelling.

4. Heavy support

Steel ribs/lattice girders provide additional structural capacity in poor ground.

5. Face protection

Forepoling, spiling or canopy systems provide advance support.

6. Water control

Drains and suitable groundwater-control measures reduce water-related instability.

The basic NATM philosophy is to allow the ground and support system to act together while controlling deformation. Immediate support, observational monitoring and adjustment of support are important principles.

7. Portal Slope Stabilization

Before tunnel excavation starts, the approach slope itself must be made safe. Typical measures include:

  • Flattening of unstable slopes
  • Benching
  • Rock bolts/anchors
  • Shotcrete sealing
  • Wire mesh
  • Gabion structures
  • Retaining walls
  • Reinforced earth systems where appropriate
  • Catch drains
  • Toe protection
  • Rockfall barriers

7.1 Simplified planar sliding check

For an illustrative planar block:

\[ FOS = \frac{ cA+(W\cos\alpha-U)\tan\phi }{ W\sin\alpha } \]

where:

  • c = effective cohesion
  • A = sliding surface area
  • W = weight of block
  • α = inclination of sliding plane
  • U = water force
  • φ = effective friction angle

This is only a simplified mechanism check. Actual Himalayan slope analysis may require limit-equilibrium analysis, stereographic analysis, wedge analysis, or numerical modelling depending on geology and failure mechanism.

8. Rock Bolts and Anchors

Rock bolts are used to reinforce the surrounding rock mass and prevent loosening of blocks or wedges. ITA describes rock bolts as support elements that can provide confinement and reinforcement to the surrounding ground.

8.1 Important parameters

Parameter Design consideration
Bolt diameter Selected based on required capacity and support class
Bolt length Must extend beyond the unstable zone into competent rock
Spacing Determined from rock mass, loads and support design
Orientation Should intercept discontinuities effectively
Anchorage Mechanical, resin or cement grouting depending on system
Plate/nut Transfers load to shotcrete/mesh/rock surface

8.2 Simplified steel tensile capacity

\[ A_s = \frac{\pi d^2}{4} \] \[ P_y=A_s f_y \]

where \(d\) is bolt diameter and \(f_y\) is steel yield strength. The allowable/design resistance must be determined using the applicable design code and the actual bolt system.

8.3 Simplified pull-out capacity

For an illustrative fully grouted bolt:

\[ P_{bond}=\pi d_b L_b\tau_b \]

where:

  • db = effective bore/bond diameter
  • Lb = bonded length
  • τb = design bond stress

The value of τb should not be blindly assumed. It should be based on the grout system, rock condition, installation quality and preferably site pull-out testing.

9. Shotcrete as Portal Support

Shotcrete provides rapid surface confinement. It seals fractured rock, reduces ravelling and works particularly effectively when combined with rock bolts and mesh/fibre reinforcement.

9.1 Functions

  • Surface sealing
  • Prevention of small-block ravelling
  • Transfer of load between support elements
  • Protection from weathering
  • Reduction of water erosion
  • Formation of a composite support shell

9.2 Simple membrane calculation

For an idealized circular ring under uniform radial pressure:

\[ N=pR \] \[ \sigma=\frac{N}{t} =\frac{pR}{t} \]

where:

  • p = uniform radial pressure
  • R = tunnel radius
  • t = shotcrete thickness
  • N = circumferential membrane force per metre
Do not use this equation alone for final shotcrete design. Actual design must consider bending, eccentricity, discontinuous loads, steel fibres/mesh, joints, construction sequence, deformation, cracking, bond, water pressure and interaction with the rock mass.

10. Steel Ribs and Lattice Girders

Steel ribs or lattice girders can provide additional load-carrying capacity where rock quality is poor and deformation is expected to be significant. ITA identifies steel ribs as a "brute strength" support system, while shotcrete and bolts provide other mechanisms of ground support.

Typical components

  • Steel ribs/lattice girders
  • Foot plates or foundations
  • Blocking/contact packing
  • Shotcrete encasement
  • Rock bolts/anchors
  • Wire mesh where required

Portal steel ribs must have adequate foundations and must be properly integrated with the surrounding support system. Simply placing steel arches without ensuring load transfer can result in ineffective support.

11. Forepoling, Spiling and Canopy Support

Forepoling is an advance-support technique used when the ground ahead of the excavation face has poor stand-up time.

Advance canopy / forepoles Tunnel face Weak ground
Figure 2 – Conceptual forepoling/canopy arrangement ahead of the tunnel face.

The purpose is to create a reinforced umbrella ahead of excavation so that the next excavation round can be carried out safely.

The exact length, inclination, spacing, overlap and pipe/rod capacity must be designed according to ground conditions and construction methodology.

12. Drainage and Groundwater Control

Water is often one of the most underestimated portal hazards. A stable rock mass can deteriorate rapidly when joints become saturated or when concentrated seepage erodes soil and weak gouge.

12.1 Surface drainage

  • Catch drains above the portal cut
  • Side drains along approach slopes
  • Chutes where required
  • Toe drains
  • Cross drainage arrangements
  • Energy dissipation at outlets

12.2 Underground drainage

  • Drainage holes
  • Weep holes
  • Drainage pipes
  • Drainage composite/membrane systems
  • Collection channels
  • Sump and pumping where required

12.3 Hydrostatic pressure

\[ p=\gamma_w h \]

For water:

\[ \gamma_w \approx 9.81\,kN/m^3 \]

Therefore, for a 5 m water head:

\[ p=9.81\times5 =49.05\,kPa \]

This illustrates why drainage should be treated as a structural and geotechnical issue rather than merely a finishing item.

13. Seismic Considerations

The Himalayan region is seismically active. Tunnel portals are particularly sensitive because they combine an underground opening with an exposed slope.

Seismic design should consider:

  • Ground acceleration
  • Seismic slope stability
  • Rockfall
  • Fault crossings
  • Joint opening
  • Dynamic deformation
  • Support ductility
  • Interaction between lining and rock mass

Where seismic demand is significant, brittle support arrangements should be avoided and the complete support system should be checked for deformation compatibility.

14. Instrumentation and Monitoring

Monitoring is an essential component of observational tunnelling.

Instrument Purpose
Convergence points Measure tunnel closure/deformation
Extensometer Measure deformation within rock mass
Inclinometer Monitor slope movement
Piezometer Monitor groundwater pressure
Crack gauges Monitor surface cracking
Survey prisms Monitor portal/slope displacement
Rock-bolt load cells Monitor selected support loads

Trigger Action Response Plan

Observation Action
Normal deformation Continue monitoring
Increasing deformation rate Increase monitoring frequency and review support
Cracking / excessive convergence Stop or modify excavation and install additional support
Sudden water increase Stop unsafe activity, investigate source and implement drainage/control
Portal slope movement Restrict access and immediately reassess slope stability

15. Recommended Portal Construction Sequence

  1. Survey and setting out: Confirm portal location, alignment, levels and geological boundaries.
  2. Surface drainage: Construct catch drains and diversion arrangements before major excavation.
  3. Controlled slope excavation: Excavate in benches rather than creating a large unsupported cut.
  4. Scaling: Remove loose blocks and unstable material.
  5. Immediate support: Apply initial shotcrete and install required mesh/bolts.
  6. Portal stabilization: Construct retaining walls, anchors, gabions or other specified systems.
  7. Forepoling: Install canopy/spiling where stand-up time is inadequate.
  8. Controlled tunnel excavation: Use short excavation rounds and controlled blasting/mechanical excavation.
  9. Primary support: Install bolts, mesh, shotcrete and ribs as specified.
  10. Monitoring: Measure deformation and compare with trigger values.
  11. Adaptation: Upgrade support if actual geology is poorer than predicted.
  12. Final lining: Construct after the required ground/support behaviour and design conditions are satisfied.

16. Solved Numerical Example – Illustrative Portal Support

Example only: This example demonstrates engineering calculations. It is not a prescribed support class for Himalayan tunnels.

Given data

Parameter Value
Tunnel diameter 10 m
Tunnel radius 5 m
RQD 55%
Jn 9
Jr 2
Ja 3
Jw 0.66
SRF 2.5
Illustrative radial support pressure 50 kPa
Illustrative bolt spacing 1.5 m × 1.5 m

Step 1 – Calculate Q

\[ Q= \left(\frac{55}{9}\right) \left(\frac{2}{3}\right) \left(\frac{0.66}{2.5}\right) \] \[ Q\approx1.08 \]

This lies in the poor/very poor transition range depending on the classification convention being applied. The actual support category must be selected from the applicable current classification/support guideline, not from this single calculation alone.

Step 2 – Tributary area of one bolt

\[ A_t=1.5\times1.5=2.25\,m^2 \]

Step 3 – Load assigned to one bolt

\[ P_b=pA_t \] \[ P_b=50\times2.25 \] \[ P_b=112.5\,kN \]

Therefore, the illustrative bolt system should provide a design resistance greater than approximately 112.5 kN under the assumed load model.

Step 4 – Bolt steel capacity

Assume a 32 mm diameter steel bolt and illustrative steel yield strength of 500 MPa.

\[ A_s=\frac{\pi(32)^2}{4} \] \[ A_s=804.25\,mm^2 \]
\[ P_y=A_sf_y \] \[ P_y=804.25\times500 \] \[ P_y\approx402\,kN \]

Thus the theoretical steel yield capacity is substantially higher than the assumed 112.5 kN demand. However, the bolt system may be governed by anchorage, bond, plate, nut, corrosion allowance or rock failure rather than steel yield.

Step 5 – Illustrative bond capacity

Assume:

  • Bond diameter = 32 mm
  • Bonded length = 4 m
  • Design bond stress = 0.40 MPa
\[ P_{bond} =\pi dL\tau_b \] \[ =\pi(0.032)(4)(400) \] \[ P_{bond}\approx161\,kN \]

Factor of safety against the illustrative bolt demand:

\[ FOS_{bolt} =\frac{161}{112.5} \] \[ FOS_{bolt}\approx1.43 \]
The bond stress of 0.40 MPa is an assumed illustrative value. Actual bond capacity must be established from the grout, borehole, rock quality and pull-out testing/design provisions.

Step 6 – Simplified shotcrete membrane check

Assume:

  • Radial pressure p = 50 kPa
  • Radius R = 5 m
  • Shotcrete thickness t = 120 mm = 0.12 m
\[ N=pR \] \[ N=50\times5=250\,kN/m \]

Average membrane stress:

\[ \sigma=\frac{250}{0.12} =2083\,kPa \] \[ \sigma\approx2.08\,MPa \]

This simplified result indicates a low average membrane compression relative to a typical concrete compressive-strength order of magnitude, but this does not constitute final shotcrete design.

Step 7 – Portal slope sliding example

Assume an illustrative potential rock block:

  • W = 1500 kN
  • α = 35°
  • c = 20 kPa
  • A = 30 m²
  • U = 200 kN
  • φ = 28°
\[ FOS = \frac{ cA+(W\cos\alpha-U)\tan\phi }{ W\sin\alpha } \]
\[ FOS \approx1.33 \]

The calculated value is only an illustrative planar-block result. If the required project FOS is higher than 1.33, stabilization would be required.

Possible stabilization measures

  • Reduce slope angle
  • Provide benches
  • Install anchors/rock bolts
  • Provide drainage
  • Provide toe support
  • Use mesh and shotcrete
  • Install rockfall protection

17. Common Tunnel Portal Failure Mechanisms

Failure Cause Preventive Measure
Wedge failure Intersecting joints Pattern/systematic bolting and mesh
Plane failure Adversely dipping discontinuity Anchors, slope re-profiling and drainage
Toppling Steep discontinuities Orientation-based anchoring
Ravelling Highly fractured rock Immediate shotcrete and mesh
Face collapse Poor stand-up time Forepoling, spiling and short rounds
Portal landslide Weak soil/rock interface Benching, anchors, retaining system and drainage
Water-induced failure High seepage/pore pressure Drainage and controlled groundwater management
Rockfall Loose blocks above portal Scaling, bolts, mesh and barriers

18. DOs and DON'Ts

✅ DOs

  • Do complete geological mapping before portal excavation.
  • Do establish a chainage-wise geological model.
  • Do identify major joint sets.
  • Do install drainage before water pressure develops.
  • Do use controlled excavation/blasting.
  • Do minimize unsupported excavation length.
  • Do install primary support immediately after excavation where required.
  • Do verify bolt pull-out capacity.
  • Do monitor convergence and slope movement.
  • Do revise support when actual ground differs from predicted ground.
  • Do provide safe access and emergency escape arrangements.
  • Do maintain proper records of geology and support installed.

❌ DON'Ts

  • Don't assume that one support class is suitable for the entire tunnel.
  • Don't excavate a large portal cut without stabilization.
  • Don't ignore surface drainage.
  • Don't rely only on shotcrete when structural blocks require anchoring.
  • Don't install bolts parallel to critical discontinuities without proper engineering assessment.
  • Don't leave unstable blocks above the portal.
  • Don't use arbitrary bolt lengths without considering the unstable zone.
  • Don't increase shotcrete thickness blindly to compensate for inadequate rock reinforcement.
  • Don't continue excavation when monitoring indicates accelerating deformation.
  • Don't treat groundwater as a temporary nuisance.
  • Don't ignore weather forecasts during portal excavation in monsoon conditions.
  • Don't modify the approved support system without engineering review.

19. Portal Support QA/QC Checklist

Item Inspection requirement
Rock bolts Diameter, length, spacing, inclination and installation records
Grouting Grout mix, pressure/volume and records
Pull-out tests Specified frequency and acceptance criteria
Shotcrete Thickness, strength, rebound, bond and curing
Steel ribs Section, spacing, alignment and connection
Wire mesh Overlap, fixing and position
Drainage Gradient, outlet, blockage and discharge condition
Forepoling Length, spacing, overlap and inclination
Geology Daily face mapping and support-class verification
Monitoring Convergence/deformation readings and trend analysis

20. Real-Life Engineering Lessons from Himalayan Tunnelling

Lesson 1 – Portal support cannot be designed only from laboratory rock strength

A strong intact rock specimen can still belong to a weak rock mass if the rock contains closely spaced joints, weathering, clay filling or unfavourable joint orientation.

This is why RQD, RMR, Q, GSI and structural geology are important.

Lesson 2 – Water can convert a manageable problem into a major failure

Water can reduce effective stress, weaken infill material, increase erosion and reduce the shear resistance of discontinuities.

Therefore:

\[ \sigma'=\sigma-u \]

where \(u\) is pore-water pressure.

As pore pressure increases, effective stress can decrease, reducing available shear resistance.

Lesson 3 – The first few metres may require more attention than the tunnel interior

At the portal, the natural ground arch is interrupted by the open slope. Therefore, a support system that is adequate deeper inside the tunnel may not automatically be adequate at the portal.

Lesson 4 – Short excavation rounds are often safer in poor ground

Short rounds reduce the time for unsupported rock to deteriorate and allow support to be installed quickly.

Lesson 5 – Monitoring should influence construction

Monitoring is not merely documentation. Increasing deformation should trigger engineering review and, where necessary, modification of excavation sequence or support.

21. Illustrative Portal Support Decision Matrix

Ground condition Possible support concept
Competent, massive rock Scaling + local bolts + drainage; limited shotcrete where required
Moderately jointed rock Systematic bolts + mesh + shotcrete
Highly fractured rock Short rounds + systematic bolts + fibre shotcrete + mesh
Poor rock with low stand-up time Short rounds + forepoling/spiling + bolts + shotcrete + ribs
Loose soil/colluvium Canopy/pipe umbrella + staged excavation + structural support
Fault/shear zone Probe drilling + drainage + spiling + anchors + ribs + shotcrete
Water-bearing weak zone Drainage/probe holes + controlled excavation + reinforced support

22. Typical Portal Support Cross-Section

Benched portal slope Rock bolts Shotcrete Steel rib Surface/catch drain Tunnel opening
Figure 3 – Conceptual portal support cross-section. Actual geometry and support must be project-specific.

23. Rock-Support Interaction

The surrounding rock is not simply a dead load acting on the lining. Excavation causes redistribution of stresses and deformation around the opening.

The design objective is to maintain sufficient strength in the rock mass while providing enough support resistance to control deformation.

Conceptual sequence

Excavation → Stress redistribution → Ground deformation → Primary support mobilisation → Stabilized ground-support system

Shotcrete, bolts, ribs and anchors therefore need to be considered as a system rather than isolated items.

24. Groundwater – A Simple Engineering Assessment

For a vertical water head \(h\):

\[ p_w=\gamma_w h \]

For example:

\[ h=10m \] \[ p_w=9.81\times10 =98.1\,kPa \]

A 10 m hydraulic head can therefore generate approximately 98 kPa of water pressure if the pressure is transmitted to the support system.

This demonstrates why drainage details can have a major influence on support performance.

25. Complete Engineering Workflow

Step 1: Topographical survey

Step 2: Geological mapping

Step 3: Geotechnical investigation

Step 4: RMR / Q / GSI assessment

Step 5: Joint orientation & failure mechanism analysis

Step 6: Portal slope stability analysis

Step 7: Groundwater assessment

Step 8: Preliminary support selection

Step 9: Numerical analysis where required

Step 10: Excavation and support sequence

Step 11: Instrumentation

Step 12: Observational review

Step 13: Final support/lining verification

26. One-Page Site Checklist

  • Portal slope geological mapping completed
  • Rock/soil boundary identified
  • Major joints mapped
  • Fault/shear zones identified
  • Groundwater/seepage locations marked
  • Catch drain completed
  • Loose blocks scaled
  • Portal slope stabilized
  • Support class approved
  • Rock bolts installed as per approved drawing
  • Pull-out tests completed
  • Shotcrete thickness verified
  • Steel ribs correctly aligned
  • Forepoling installed where required
  • Monitoring points installed
  • Convergence readings recorded
  • Rainfall/weather conditions monitored
  • Emergency access maintained

27. Conclusion

Tunnel portal construction in the Himalayas requires a fundamentally different mindset from ordinary excavation. The portal is a combined slope + rock-mass + groundwater + tunnel-face + seismic problem.

A safe portal support system should therefore combine:

⛰️ Stable slope geometry
🪨 Rock reinforcement
🧱 Shotcrete confinement
🏗️ Steel ribs where required
🌲 Forepoling/canopy support
💧 Effective drainage
📡 Instrumentation
👷 Controlled construction

The most important principle is:

"Do not wait for the portal to fail before increasing support."

Observe the ground, classify it, support it early, control water and continuously compare actual behaviour with the design assumptions.

28. Technical References and Further Reading

  1. Indian Roads Congress – IRC:SP:91, Guidelines for Road Tunnels.
  2. Indian Roads Congress – IRC:SP:84, Manual for Specifications and Standards for Four-Laning of National Highways through Public Private Partnership.
  3. Bureau of Indian Standards – IS 13365 series, Quantitative Classification System of Rock Mass.
  4. ITA-AITES – Guidance on tunnel support systems and geotechnical characterization.
  5. Indian Railway Institute of Civil Engineering – Tunnel Design and Tunnel Supports.
  6. Relevant project-specific Employer's Requirements, Geological Reports, Design Basis Reports and approved Tunnel Support Class drawings.

Always use the latest applicable edition of the relevant code, specification and project contract documents.

© YogiPWD – Civil Engineering Knowledge Resource. This article is intended for technical education and preliminary engineering reference. Final tunnel design shall be carried out by qualified geotechnical, tunnelling and structural engineers based on project-specific investigations.