PSC Girder Stressing & Grouting
From Tendon Tensioning to Long-Term Structural Durability
"Right Force + Correct Elongation + Complete Grouting = Durable Post-Tensioned Concrete Girder."
1 Before Stressing Protocols
- Verify concrete compressive strength has achieved the specified minimum stressing strength ($f_{cj}$, typically $\ge 0.8 f_{ck}$).
- Inspect tendon ducts using compressed air or mandrel pulling for alignment and blockage free passages.
- Clean anchorage plates, trumpet openings, and wedges; clear off rust, slurry, or debris.
- Validate hydraulic jack & pressure gauge calibration charts (must be within valid 6-month window).
- Establish clear exclusion safety zones behind live-end anchorages prior to pressurization.
2 Stressing Execution Sequence
- Initial Seating: Apply 10% target force to take up slack and establish baseline mark ($L_0$).
- Incremental Stressing: Raise pressure in 20% increments (e.g., 20%, 40%, 60%, 80%, 100%).
- Elongation Measurement: Measure extension at each stage to monitor force-displacement linearity.
- Target Force Verification: Hold target pressure for 5 minutes; verify maximum elongation variance ($\le \pm 5\%$).
- Wedge Seating / Lock-Off: Release hydraulic pressure allowing wedges to bite and seat into anchor block.
- Jack Release: Retract cylinder, measure final wedge draw-in/slip, and record final field logs.
Grouting serves a dual purpose: providing direct bond between prestressing steel and structural concrete, and shielding high-strength strands from aggressive environmental corrosion.
Grouting Sequence:
| Test / Property | Acceptance Limit |
|---|---|
| Water/Cement Ratio | $\le 0.40$ max |
| Grout Temperature | $10^\circ\text{C}$ to $25^\circ\text{C}$ |
| 7-Day Compressive Strength | $\ge 27\text{ MPa}$ |
| 28-Day Compressive Strength | $\ge 35\text{ MPa}$ |
| 28-Day Volume Change | $\le +0.2\%$ expansion |
| 24-hr Free Bleeding | $\le 0.5\%$ (must re-absorb) |
| Cone Fluidity (Flow Time) | $11\text{ s} - 25\text{ s}$ |
| Fluidity Retention (30 min) | $\le 20\%$ change |
| Chloride Content | $\le 0.10\%$ by cement wt |
Stressing Solely by Pressure Gauge
Relying only on hydraulic pressure without verifying physical elongation hides structural friction losses and strand bind.
Ignoring Elongation Deviation
Proceeding when theoretical vs measured variance exceeds $\pm 5\%$ leads to under-stressing or strand breakage.
Adding Water to Improve Grout Flow
Diluting grout increases voids, severe bleeding, and micro-cracking, destroying corrosion protection.
Premature Vent Closure
Closing vents before full, air-free grout discharge creates trapped air pockets and localized strand corrosion.
Site Engineer's Key Takeaway
Verified Jack Calibration + Accurate Elongation Measurements + Full Lock-off Seating + High-Quality Colloidal Grouting = Long-Life Structural Integrity.