Tentative Road Works costs as per SSR 2022-23

Tentative Road Works Costs SSR 2022-23

Tentative Road Works Costs as per SSR 2022-23

ESTIMATED COST FOR RENEWAL / WIDENING / REBUILT / C D WORK & MINOR BRIDGE
प्रति किमी दर
Estimated Cost based on Current SSR/WEF: 25/7/2022 (SSR-2022-23)
No Road Category Width of Road (m) Rate/KM (Lakh) Including 18% GST, 3% Contingencies & 1% Labour & Road Safety Charges Total Provided Crust Scope of Work
Rebuilt Work for B.C Portion (CBR 3% to 5%)
1 MDR 3.75 125 350 MM 200 mm Earthwork, 300 mm Cement Treated Soil Sub Base (CTSB), 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2 MDR / SH 5.5 205
3 MDR / SH 7 255
Rebuilt Work with Lime Stabilisation for Improving Subgrade
1 MDR 3.75 95 350 MM 200 mm Earthwork, 300 mm Lime Stabilisation, 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2 MDR / SH 5.5 125
3 MDR / SH 7 155
Rebuilt Work with CTSB + WMM
1 MDR 3.75 100 450 MM 300 mm CTSB, 100 mm WMM, 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2 MDR / SH 5.5 135
3 MDR / SH 7 165
Renewal Work
1 MDR 3.75 45 75 MM Site Cleaning, Picking, Open Excavated Gutter, 75 mm MPM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2 MDR / SH 5.5 60
3 MDR / SH 7 73
4 SH 10 100
Widening Work
1 MDR / SH 3.75 TO 5.50 148 450 MM Site Cleaning, Open Excavated Gutter, Earthwork, 150 mm GSB, 150 mm GR-I, 75 mm GR-II, 75 mm MPM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc.
2 MDR / SH 5.50 TO 7.00 159
C.C. Road
1 MDR 3.75 213.5 600 MM Site Cleaning, 150 mm GSB, 150 mm DLC, M-40 - 300 mm PQC, HM Side Shoulder, Road Furniture etc.
Built-up Drain
1 1.50 m Width Per Running Meter 20000.00 / Rmt M-20 Site Cleaning, Excavation, 80 mm Soiling, M-10 PCC, M-20 Head Wall & Foundation, M-20 Slab, TMT, Weep Hole etc.
C.D. Work
1 STATE HIGHWAY (12.00 M WIDTH) 1 Vent 1200 mm 9.5 M-20 Site Cleaning, Excavation, 80 mm Soiling, M-10 PCC, M-20 Face Wall, NP-3 Pipe, Back Filling etc.
Minor Bridge Work
1 SH (12.00 M) -- 10.00 Lakh/M Cost including both side 50 m approaches with diversion.

 

Sr. No. Particular of Works Cost in Rupees Mode of Measurement
1 New road CONSTRUCTION 3.75 M WITHOUT SHOULDERS 79,28,665.00 Per KM
2 New road CONSTRUCTION 5.5 M WITHOUT SHOULDERS 1,16,28,705.00 Per KM
3 New road CONSTRUCTION 7.0 M WITHOUT SHOULDERS 1,48,00,171.00 Per KM
4 Renewal 3.75 M BM and BC 29,83,925.00 Per KM
5 Renewal 5.5 M BM and BC 43,76,422.00 Per KM
6 Renewal 7.0M BM and BC 55,69,991.00 Per KM
7 Renewal 3.75 M BM and Carpet Sealcoat 24,59,795.00 Per KM
8 Renewal 5.5 M BM and Carpet Sealcoat 36,07,698.00 Per KM
9 Renewal 7.0 M BM and Carpet Sealcoat 45,91,615.00 Per KM
10 Renewal 3.75 M MPM and Carpet Sealcoat 22,54,314.00 Per KM
11 Renewal 5.5 M MPM and Carpet Sealcoat 33,06,325.00 Per KM
12 Renewal 7.0 M MPM and Carpet Sealcoat 42,08,050.00 Per KM
13 WIDENING CONSTRUCTION 3.75 M TO 5.5 M WITHOUT SHOULDERS 40,69,006.00 Per KM
14 WIDENING CONSTRUCTION 5.5 M TO 7.0 M WITHOUT SHOULDERS 34,87,718.00 Per KM
15 WIDENING CONSTRUCTION 7.0 M TO 10 M WITHOUT SHOULDERS 69,75,436.00 Per KM
16 Pothole Filling upto 75 mm with MPM only 321.00 Per sq.m
17 Pothole Filling upto 150 mm with MPM only 642.00 Per sq.m
18 Pothole Filling upto 50 mm with BM only 376.00 Per sq.m
19 Pothole Filling upto 150 mm with BM only 1,087.00 Per sq.m
20 Pothole Filling upto 150 mm on OGC road with MPM and Grade 1 material 479.00 Per sq.m
21 Pothole Filling upto 300mm on OGC road with MPM and Grade 1 material 877.00 Per sq.m
22 Pothole Filling upto 150 mm on OGC road with BM and Grade 1 material 634.00 Per sq.m
23 Pothole Filling upto 300 mm on OGC road with BM and Grade 1 material 992.00 Per sq.m

 