| ESTIMATED COST FOR RENEWAL / WIDENING / REBUILT / C D WORK & MINOR BRIDGE |
| प्रति किमी दर |
| Estimated Cost based on Current SSR/WEF: 25/7/2022 (SSR-2022-23) |
| No |
Road Category |
Width of Road (m) |
Rate/KM (Lakh) Including 18% GST, 3% Contingencies & 1% Labour & Road Safety Charges |
Total Provided Crust |
Scope of Work |
| Rebuilt Work for B.C Portion (CBR 3% to 5%) |
| 1 |
MDR |
3.75 |
125 |
350 MM |
200 mm Earthwork, 300 mm Cement Treated Soil Sub Base (CTSB), 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc. |
| 2 |
MDR / SH |
5.5 |
205 |
|
|
| 3 |
MDR / SH |
7 |
255 |
|
|
| Rebuilt Work with Lime Stabilisation for Improving Subgrade |
| 1 |
MDR |
3.75 |
95 |
350 MM |
200 mm Earthwork, 300 mm Lime Stabilisation, 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc. |
| 2 |
MDR / SH |
5.5 |
125 |
|
|
| 3 |
MDR / SH |
7 |
155 |
|
|
| Rebuilt Work with CTSB + WMM |
| 1 |
MDR |
3.75 |
100 |
450 MM |
300 mm CTSB, 100 mm WMM, 50 mm BM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc. |
| 2 |
MDR / SH |
5.5 |
135 |
|
|
| 3 |
MDR / SH |
7 |
165 |
|
|
| Renewal Work |
| 1 |
MDR |
3.75 |
45 |
75 MM |
Site Cleaning, Picking, Open Excavated Gutter, 75 mm MPM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc. |
| 2 |
MDR / SH |
5.5 |
60 |
|
|
| 3 |
MDR / SH |
7 |
73 |
|
|
| 4 |
SH |
10 |
100 |
|
|
| Widening Work |
| 1 |
MDR / SH |
3.75 TO 5.50 |
148 |
450 MM |
Site Cleaning, Open Excavated Gutter, Earthwork, 150 mm GSB, 150 mm GR-I, 75 mm GR-II, 75 mm MPM, 20 mm OGC, LSC, Tack Coat, HM Side Shoulder, Road Furniture etc. |
| 2 |
MDR / SH |
5.50 TO 7.00 |
159 |
|
|
| C.C. Road |
| 1 |
MDR |
3.75 |
213.5 |
600 MM |
Site Cleaning, 150 mm GSB, 150 mm DLC, M-40 - 300 mm PQC, HM Side Shoulder, Road Furniture etc. |
| Built-up Drain |
| 1 |
1.50 m Width |
Per Running Meter |
20000.00 / Rmt |
M-20 |
Site Cleaning, Excavation, 80 mm Soiling, M-10 PCC, M-20 Head Wall & Foundation, M-20 Slab, TMT, Weep Hole etc. |
| C.D. Work |
| 1 |
STATE HIGHWAY (12.00 M WIDTH) |
1 Vent 1200 mm |
9.5 |
M-20 |
Site Cleaning, Excavation, 80 mm Soiling, M-10 PCC, M-20 Face Wall, NP-3 Pipe, Back Filling etc. |
| Minor Bridge Work |
| 1 |
SH (12.00 M) |
-- |
10.00 Lakh/M |
|
Cost including both side 50 m approaches with diversion. |