Estimates Varies as per user requirements, but the basic requirements remain same.

Basic Requirements:

  • 1) Number of People for which septic tank is to be constructed: 25
  • 2) Septic Tank Wall: 1st class Brickwork in 1:4 Mortar
  • 3) Floor/Foundation: 1:3:6 Cement concrete
  • 4) Inner Plaster: 12 mm in 1:3 Cement Mortar
  • 5) Flooring Plaster: 20 mm in 1:3 Mortar with water proofing compounds
  • 6) Upper & Lower portion of soak pit: 2nd class Brickwork in 1:6 Cement mortar
  • 7) Middle portion of Soak pit: Dry Brickwork
  • 8) Roof Covering slabs & Baffle wall: Precast R.C.C.
  • 9) Length of Connecting pipe from Latrine seat: 3 m
Design :-
Capacity of tank @ 0.08 cu.m per user = 25 x 0.08 = 2 cu.m
Taking Depth of water as 1.4 m the floor area of tank = 2/1.4 = 1.428 sq.m
Taking length as 2 times the breadth = L x B = 1.428 sq.m
2B x B = 1.428 sq.m
B = sqrt (1.428/2) = 0.9449 m say 0.9 m
L = 2B = 1.8 m say 2 m
Required Floor Area = 1.428 sq.m
Provided Floor Area = 1.8 sq.m
Required Area < Provided Area, Hence OK
Taking Free Board of 0.3m Hence Total Depth of Tank = 1.4 + 0.3 m = 1.7 m
Drawing Estimate:-

Estimate For Septic Tank (Soak pit Not Included)

Abstract
Description Quantity Unit Rate Amount
Earthwork Excavation ... ... ...
P.C.C. 1:3:6 ... ... ...
Brickwork 1:4 ... ... ...
Sr No. Quantity Unit Description of Item Rate Amount (₹)
1.1 11.2 Square Metre Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300mm... (Item No. 2.09) 13.2 147.84
1.2 11.22 Cubic Metre Excavation for foundation in earth, soil of all types... By Manual Means (Item No. 21.01) 262.9 2949.74
1.3 2.992 Cubic Metre Excavation for foundation in earth... (Lift from 1.5m to 3.0m) By Manual Means (Item No. 21.03) 345.4 1033.43
1.4 1.12 Cubic Metre Providing and laying Cast in situ/Ready Mix cement concrete in M-10... (Item No. 24.01) 6812.7 7630.23
1.5 2.712 Cubic Metre Providing first class Burnt Brick masonry... in pillars of rectangular or square shape... (Item No. 27.08) 10817.15 29336.11
1.6 0.356 Cubic Metre Providing and laying in situ/ready mix controlled grade of M15... (Item No. 12.55) 8620.05 3068.74
1.7 0.032 Metric Tonne Providing, cutting, bending, hooking, tying and laying in position TMT FE 500 steel bars... (Item No. 14.01) 97340.1 3114.89
1.8 17.49 Square Metre Providing sand faced plaster externally in cement mortar... (Item No. 32.11) 713.65 12481.74
1.9 10 Running Metre Providing and laying for 150mm dia salt glazed stoneware pipe including fittings... (Item No. 42.04) 454.65 4546.5
1.10 1 Number Providing and fixing 8cm C.I. Nahani Trap including C.I. grating... (Item No. 41.79) 895.55 895.55
1.11 2 Running Metre Providing and fixing on walls/ceiling/floor 15mm dia. CPVC pipe... (Item No. 42.55) 292.6 585.2
1.12 1 Number Providing and fixing in position UPVC ultra violet stabilized 110mm outer diameter cowl dome... (Item No. 43.25) 185.9 185.9
Total Amount 65975.87
Measurements
Sr No. Item No. Category Description Unit
1.1 2.09 Road Sub grade Clearing and grubbing road land including uprooting vegetation, trees up to 300mm... Sq.M.
Description of Measurement No. Length Width Height Quantity
Main Area 3.40+0.6 2.20+0.6 11.20
Net Quantity: 11.20 Sq.M.
1.2 21.01 Excavation Excavation for foundation in earth, soil, etc. (Lift 0.00 to 1.50m) Cu.M.
HEIGHT = TANK H + SLABS 1 2.80+0.6 1.60+0.6 0.20+1.70 14.212
RESTRICTION DEDUCTION -1 3.4 2.2 0.4 -2.992
Net Quantity: 11.22 Cu.M.
1.5 27.08 Brick Masonry First class Burnt Brick masonry in CM 1:4... Cu.M.
Long Walls (Step 1) 2 2.60 0.30 0.60 0.936
Long Walls (Step 2) 2 2.40 0.20 1.10 1.056
Net Quantity: 2.712 Cu.M.
Rate Analysis
Sr. Item No Description of Item / Component Rate / Lead Unit
1.4 24.01 Providing and laying M-10 Cement Concrete for foundation including PLC SCADA mixer, etc. 5830.00 Cu.M.
10% Hilly Area Charges 583.00
20mm Metal Lead Charges (0.24 x 263.19) 63.17
Cement Lead Charges (0.22 x 164.99) 36.30
COMPLETED RATE (1.4): 6812.70 Cu.M.
1.7 14.01 TMT FE 500 steel bars reinforcement complete. 88341.00 M.T.
10% Hilly Area Charges 8834.10
COMPLETED RATE (1.7): 97340.10 M.T.
Testing Abstract
Sr. Description of Laboratory Tests Frequency Rate Amount
2.1 CEMENT: Consistency, Fineness, Specific Gravity, Setting Time, Strength, Soundness. 1 Set 3300.00 3300.00
2.6 CEMENT CONCRETE: Compressive strength and Mix Design.
Compressive strength (Set of 3 cubes) 1 600.00 600.00
Concrete Mix Design (Full basic material tests) 1 12100.00 12100.00
TOTAL TESTING CHARGES: 31200.00
Testing Measurements
Sr. Description of Tests Frequency Consumption Tests Req. Unit
2.1 Laboratory Testing on CEMENT (Consistency, Strength, etc.)
Standard Frequency: 1/50 MT 1/50 MT 0.95 1 MT
2.6 Laboratory Testing on CEMENT CONCRETE
Compressive strength (Set of 3 cubes) Per Set 1.12 1 Cu.M.
Concrete Mix Design (All basic materials) Per Grade 1.00 1 Design
Lead Charges (Source: Nashik)
Sr. Material Lead (KM) Lead Charges SSR Rate Total Rate Unit
1 12mm Metal 5 263.19 115.00 378.19 Cu.M.
5 Cement 5 164.99 4700.00 4864.99 MT
Recapulation Sheet
Code Particulars of Works Basis Amount (INR)
A Main Work (Septic Tank Construction) 65,975.87
Sub-Total (A) 65,975.87
B Testing & Royalties
Construction Material Testing 31,200.00
Other Minerals (Royalties) 169.49
Sub-Total (B) 31,369.49
C Provisions & Taxes
Labor Insurance 0.5% 486.73
GST (Goods & Service Tax) 18% 17,522.17
TOTAL COST OF PROJECT (A+B+C) 1,15,354.00