Sample calculations for the design of a Tremix concrete road as per Indian standards for Estimate Purpose:

1. Subgrade Preparation:

Assuming the subgrade is compacted to 95% density, sub-base thickness =100mm, bulk density =1600 kg/m³

Weight = Thickness × Density × Compaction

= 0.1 × 1600 × 0.95 = 152 kg/m²

2. Concrete Mix Design (M30):

Water cement ratio = 0.45

Cement = 350 kg/m³

Water = 0.45 × 350 = 157.5 kg/m³

Fine aggregate:

= 0.5 × (1-0.45) × 350 /1600 = 73.44 kg/m³

Coarse aggregate:

= 350 +73.44 +157.5 –2 = 579.94 kg/m³

3. Design Parameters:

Design life = 15 years

Traffic = 450 PCU

Subgrade CBR = 5%

WMM CBR = 60%

WMM thickness =100mm

M10 base =150mm

Tremix layer =200mm

Grade = M30

Total traffic = 15 × 450 = 6750 MSA

Axle load:

(450×1000)/3000 = 150 axles/day

Design traffic:

= 6750×10⁶ /(365×24) = 768 MSA

CBR check WMM:

= (768×10⁶/10⁶)×(100/1000) = 76.8

Available CBR = 60% → SAFE

M10 base thickness:

= (768×10⁶ /(5×8.2))^(1/3) = 225 mm

Provided =150mm → SAFE

Tremix thickness:

= (768×10⁶ /(5×6))^(1/3) = 191 mm

Provided =200mm → SAFE

Reinforcement:

Bar =12mm, spacing =200mm

Area = Ï€/4 ×12² = 113.10 mm²

Required steel:

Asf =425.14 mm²

Bars =425.14/113.10 = 3.76 ≈ 4 bars

Provide 4 numbers of 12mm bars per meter width

Abstract

Sr No. Quantity Unit Description of Item Rate Amount in Rupees
1.1761.25Cubic Metre Excavation for roadway in earth... (Item No. 2.11) 130.999647.63
1.2187.5Cubic Metre Wet Mix Macadam... (Item No. 3.23) 2824.1529518.75
1.3281.25Cubic Metre Providing and laying PCC M-10... (Item No. 24.01) 7042.151980604.69
1.41875Square Metre Providing LDPE sheet... (Item No. 5.19) 3361875
1.5375Cubic Metre Providing M-30 Tremix concrete... (Item No. 5.22b) 10136.23801075
1.652.988Metric Tonne TMT FE500 reinforcement... (Item No. 14.01) 974585164104.5
Total Amount 11636825.57

Measurements

Sr No. Item No. Category Description No. Length Width Height Quantity Unit
1.12.11Road Subgrade Excavation for roadway... 15003.75+0.60.35 761.25Cu.M.
Net Quantity 761.25Cu.M.
1.23.23Sub Base & Base Wet Mix Macadam... 15003.750.1 187.5Cu.M.
Net Quantity 187.5Cu.M.
1.324.01PCC M-10 concrete... 15003.750.15 281.25Cu.M.
Net Quantity 281.25Cu.M.
1.45.19Rigid Pavement LDPE sheet 5003.75 1875Sq.M.
Net Quantity 1875Sq.M.
1.55.22bRigid Pavement M30 Tremix concrete 15003.750.2 375Cu.M.
Net Quantity 375Cu.M.
1.614.01Super Structure Reinforcement steel (500/4)/10003.750.78512x12 52.988MT
Net Quantity 52.988MT

Comparative chart for Tremix concrete roads vs Pavement Quality Concrete roads

Parameter Tremix Concrete Road Design Pavement Quality Concrete Road Design
Subgrade preparation Subgrade compacted to required density with minimum 100 mm granular sub-base. Subgrade compacted to required density with minimum 150 mm granular sub-base.
Concrete mix design Minimum compressive strength 30 MPa, maximum aggregate size 20 mm. Minimum compressive strength 35 MPa, maximum aggregate size 20 mm.
Reinforcement As per design requirement. As per Indian standards, CRPC requires minimum 0.15% steel reinforcement placed in bottom third.
Thickness 150 – 200 mm 200 – 250 mm
Joint spacing Generally 4–6 m. As per Indian standards, maximum spacing 5 m. Depends on traffic and climate. As per Indian standards, maximum spacing 5 m.
Joint type Dowel bars generally used. Tie bars or dowel bars used.
Curing Wet curing minimum 7 days. As per Indian standards, minimum 14 days. Wet burlap or curing compound. As per Indian standards, minimum 7 days.
Surface finish Smooth and uniform. Textured surface possible for skid resistance and aesthetics.
Construction method Tremix machine used for laying and leveling. Paver or slipform machine used.
Cost Generally lower. Generally higher.

Selection depends on traffic volume, climate, soil conditions and budget. Both systems have advantages and should be chosen after technical evaluation.