Dewatering Calculator tool

Excavation Inflow • Rainfall • Pump Selection • TDH • Sump Storage • Well-Point Screening

Civil Engineering Design-Support Tool

1. Project & Excavation Inputs

Used for preliminary observed inflow estimation.

2. Rainfall & Catchment Contribution

Qrain = P × A × C / 1000
where P = rainfall intensity in mm/hr.

3. Groundwater / Seepage Inputs

Enter a hydrogeological estimate if available.

4. Pump Selection & Total Dynamic Head

Use pump-system calculation or pipe-loss analysis.
TDH = Static Head + Friction Head + Minor-Loss Head

5. Duty / Standby Philosophy

Standby pumps are a reliability provision. Final standby requirements should follow project specifications, risk assessment and the approved dewatering method statement rather than being treated as a universal numerical codal requirement.

6. Concrete-Pour Protection

7. Well-Point Screening Inputs

Actual well-point design requires soil permeability, aquifer thickness, groundwater level, well spacing, filter characteristics, drawdown requirements and pump/vacuum characteristics. The calculation below is only a screening estimate.

8. Dewatering System Schematic

Existing Ground Groundwater / Inflow Sump + Pump Discharge Pipe Rainfall / Runoff Conceptual schematic – not for construction drawing

9. Design Summary

Enter the design data and calculate.
Excavation Volume
—
Estimated Inflow
—
Pump / Unit
—
Total Duty Capacity
—

10. Detailed Engineering Calculation

The detailed calculation will appear here after the design is calculated.

11. Sump Storage Check

Calculate the system to obtain sump-storage requirements.

12. Well-Point Screening

Calculate the system to obtain well-point screening.

13. Engineering Warnings & Checks

  • Calculation not yet performed.

14. Dewatering Design Guidance

14.1 Basic Water Balance

Qdesign = SF × (Qgroundwater + Qrainfall + Qother)

The dewatering system should have sufficient effective pumping capacity to control the design inflow while maintaining the required excavation water level.

14.2 Total Dynamic Head

TDH = Hstatic + Hfriction + Hminor

Pump selection should ultimately be made from the manufacturer's pump curve at the calculated operating point, rather than from motor horsepower alone.

14.3 Pump Hydraulic Power

P = ρgQH / η

where ρ is water density, g is gravitational acceleration, Q is discharge in m³/s, H is TDH in metres and η is overall pump efficiency.

14.4 Concrete-Pour Protection

During critical concreting operations, groundwater should not be allowed to wash cement paste, disturb reinforcement, contaminate the concrete placement zone or cause instability of the excavation formation. The required pumping duration should therefore include the actual pour duration plus the specified post-pour protection period.

15. Dewatering — Do's

  • Measure actual groundwater inflow wherever practical.
  • Keep at least one operational backup arrangement for critical works.
  • Check pump performance at the actual TDH.
  • Provide adequate discharge routing and erosion protection.
  • Monitor excavation stability and piping/boiling.
  • Protect pumps from sediment and debris.
  • Maintain emergency power where loss of pumping can affect safety.
  • Monitor groundwater levels outside the excavation where settlement could be a concern.

16. Dewatering — Don'ts

  • Do not select pumps solely by HP rating.
  • Do not ignore friction and minor losses.
  • Do not assume rainfall contribution is zero during monsoon operations.
  • Do not discharge muddy water without appropriate sediment control.
  • Do not place sumps where pumping can undermine foundations or slopes.
  • Do not assume well points will work effectively in every soil.
  • Do not rely on a single pump for critical concrete operations.
  • Do not use this preliminary calculator as a substitute for detailed hydrogeological design.