Dewatering Calculator tool
Excavation Inflow • Rainfall • Pump Selection • TDH • Sump Storage • Well-Point Screening
Civil Engineering Design-Support Tool1. Project & Excavation Inputs
2. Rainfall & Catchment Contribution
where P = rainfall intensity in mm/hr.
3. Groundwater / Seepage Inputs
4. Pump Selection & Total Dynamic Head
5. Duty / Standby Philosophy
6. Concrete-Pour Protection
7. Well-Point Screening Inputs
8. Dewatering System Schematic
9. Design Summary
10. Detailed Engineering Calculation
The detailed calculation will appear here after the design is calculated.
11. Sump Storage Check
12. Well-Point Screening
13. Engineering Warnings & Checks
- Calculation not yet performed.
14. Dewatering Design Guidance
14.1 Basic Water Balance
The dewatering system should have sufficient effective pumping capacity to control the design inflow while maintaining the required excavation water level.
14.2 Total Dynamic Head
Pump selection should ultimately be made from the manufacturer's pump curve at the calculated operating point, rather than from motor horsepower alone.
14.3 Pump Hydraulic Power
where ρ is water density, g is gravitational acceleration, Q is discharge in m³/s, H is TDH in metres and η is overall pump efficiency.
14.4 Concrete-Pour Protection
During critical concreting operations, groundwater should not be allowed to wash cement paste, disturb reinforcement, contaminate the concrete placement zone or cause instability of the excavation formation. The required pumping duration should therefore include the actual pour duration plus the specified post-pour protection period.
15. Dewatering — Do's
- Measure actual groundwater inflow wherever practical.
- Keep at least one operational backup arrangement for critical works.
- Check pump performance at the actual TDH.
- Provide adequate discharge routing and erosion protection.
- Monitor excavation stability and piping/boiling.
- Protect pumps from sediment and debris.
- Maintain emergency power where loss of pumping can affect safety.
- Monitor groundwater levels outside the excavation where settlement could be a concern.
16. Dewatering — Don'ts
- Do not select pumps solely by HP rating.
- Do not ignore friction and minor losses.
- Do not assume rainfall contribution is zero during monsoon operations.
- Do not discharge muddy water without appropriate sediment control.
- Do not place sumps where pumping can undermine foundations or slopes.
- Do not assume well points will work effectively in every soil.
- Do not rely on a single pump for critical concrete operations.
- Do not use this preliminary calculator as a substitute for detailed hydrogeological design.
0 Comments
If you have any doubts, suggestions , corrections etc. let me know