Summary: -
₹0 / 0%
Activity Management
| Activity | Timeline | Total Qty | Achieved Qty | Exp. vs Act. % | Cost Achieved | Status | Actions |
|---|
Construction PM – Multi-Project Management Suite
The provided code implements a browser-based construction project management system. It allows engineers or project managers to manage multiple infrastructure projects, track activities, calculate cost progress, visualize completion percentages, and export progress reports.
The entire system runs inside a single HTML file using JavaScript, Local Storage, Chart.js visualizations, and PDF generation. No backend server is required.
1. External Libraries Used
The application integrates several JavaScript libraries for advanced functionality.
Chart.js
Chart.js is used to generate the progress comparison chart showing expected vs actual completion percentage for each activity.
jsPDF
jsPDF generates downloadable PDF reports summarizing project progress.
jsPDF AutoTable
This plugin creates formatted tables in the exported PDF.
2. Layout and Interface Design
The interface is built using standard HTML and CSS. The layout follows a card-based dashboard design.
Main Interface Components
- Project selector and management controls
- Project information card
- Milestone management
- Activity entry form
- Activity tracking table
- Progress chart
- Export/Import and PDF generation tools
CSS styles define the overall appearance including typography, card layouts, buttons, tables, and color-coded status indicators.
3. Project Data Structure
All application data is stored in a JavaScript object called library.
let library = {
currentProjectId: null,
projects: {}
};
Each project contains:
- Project ID
- Project name
- Total budget
- Activities list
- Milestones
- Reached milestones
project = {
id: "proj_123",
name: "Highway Project",
budget: 100000,
activities: [],
milestones: [25,50,75],
reachedMilestones: []
}
4. Local Storage Persistence
The application saves data using the browser's Local Storage API.
localStorage.setItem('construction_library', JSON.stringify(library));
When the page loads:
- The stored JSON data is retrieved.
- Projects are restored automatically.
- If no project exists, a default project is created.
5. Activity Categories
The system organizes construction tasks into structured groups such as:
- Roadwork Layers
- Structures
- Bridges
- Drainage
- Safety Components
- River Training Works
const activityGroups = {
"Roadwork - Layers": ["Excavation","GSB","WMM"],
"Bridges": ["Foundation","Substructure","Superstructure"]
};
This structure ensures standardized activity naming across projects.
6. Activity Entry System
Users can add or update construction activities using the activity form.
Each activity stores:- Activity name
- Start date
- End date
- Total quantity
- Achieved quantity
- Unit cost
{
name: "Wet Mix Macadam",
start: "2026-01-01",
end: "2026-02-01",
totalQty: 1000,
achievedQty: 400,
unitCost: 120
}
The application calculates cost automatically:
cost = achievedQty × unitCost
7. Progress Calculation Algorithm
The function calcStats() determines activity performance.
Expected Progress
Based on time elapsed:expected = (days passed / total days) × 100
Actual Progress
Based on quantity completed:actual = (achievedQty / totalQty) × 100
Status Evaluation
- If actual progress is significantly lower → Behind
- If equal or greater → On Track
- Green = Ahead/On track
- Red = Behind schedule
8. Milestone Tracking
Milestones represent percentage thresholds of the project budget.
Example:- 25%
- 50%
- 75%
targetAmount = (milestonePercent / 100) × projectBudgetIf the total spent exceeds the target amount, the milestone is marked as achieved. Achieved milestones turn green in the interface.
9. Progress Visualization
Chart.js generates a dynamic bar chart comparing expected vs actual progress.
Two datasets are rendered:- Expected progress (grey)
- Actual progress (blue)
10. JSON Backup and Restore
The application supports exporting and importing project data.
Export
Creates a downloadable JSON backup file.Project progress backup dated YYYY-MM-DD.json
Import
The system reads the JSON file and merges the imported projects with existing data. This enables:- Data backup
- Sharing projects between computers
- Long-term archiving
11. PDF Report Generation
Clicking the Download PDF button generates a formatted project report.
The report includes:- Project name
- Report date
- Total budget
- Total expenditure
- Activity progress table
- Embedded progress chart
- jsPDF
- jsPDF AutoTable
12. Multi-Project Capability
The tool allows managing multiple projects simultaneously.
Features include:- Create new projects
- Rename projects
- Switch between projects
- Delete projects
- Activities
- Budget
- Milestones
- Progress records
13. Advantages of This System
- Runs entirely in a web browser
- No installation required
- No server or database required
- Instant visual progress tracking
- Automatic cost calculations
- Exportable reports