YogiPWD

Block Estimate Rates

PWD Block Estimate (2022-23)

PWD Block Estimate Calculator (2022-23)

Ghat +15%, Tribal +10%, Corp +5%, Gadchiroli +20%

Road construction / renewal works (2022–23)

Sl No Item of Work Details Proposed Rate 2022-23
1 Village Road Roadway: 7.50 m, Carriageway: 3.00 m, BC Soil (Per Km) 834000.00
1 Village Road Roadway: 7.50 m, Carriageway: 3.00 m, Non BC Soil (Per Km) 681800.00
2 Other District & Major District Road upto WBM Roadway: 7.50 m, Carriageway: 3.75 m, BC Soil (Per Km) 1010100.00
2 Other District & Major District Road upto WBM Roadway: 7.50 m, Carriageway: 3.75 m, Non BC Soil (Per Km) 843700.00
3 State Highway upto WBM Roadway: 7.50 m, Carriageway: 3.75 m, BC Soil (Per Km) 1413000.00
3 State Highway upto WBM Roadway: 7.50 m, Carriageway: 3.75 m, Non BC Soil (Per Km) 1204500.00
4A Road Renewals - VR One Metal Layer WBM (7.5 cm compacted, 3.00 m wide) 976000.00
4B Road Renewals - ORD/MDR One Metal Layer WBM (7.5 cm compacted, 3.75 m wide) 1200000.00
4C Road Renewals - SH One Metal Layer WBM (7.5 cm compacted, 5.50 m wide) 1790000.00
5 Modified Penetration Macadam (MPM) 75 mm thick, 3.75 m width, Over WBM 1418250.00
5 Modified Penetration Macadam (MPM) 75 mm thick, 3.75 m width, Over BT 1500938.00
6 Built up Spray Grout (BUSG) 75 mm thick, 3.75 m width, Over WBM 1513250.00
6 Built up Spray Grout (BUSG) 75 mm thick, 3.75 m width, Over BT 1701000.00
7 Modified Penetration Macadam (MPM) 50 mm thick, 3.75 m width, Over WBM 1058438.00
7 Modified Penetration Macadam (MPM) 50 mm thick, 3.75 m width, Over BT 1197188.00
8 Single Coat Surface Dressing 3.75 m Carriageway, Over WBM 380250.00
8 Single Coat Surface Dressing 3.75 m Carriageway, Over BT 387000.00
9 20 mm Premix Carpet (Open graded premix surfacing) with liquid seal coat (Hot Mix laid, 3.75 m wide) Over WBM 1228313.00
9 20 mm Premix Carpet (Open graded premix surfacing) with liquid seal coat (Hot Mix laid, 3.75 m wide) Over BT 1214626.00
10 50 mm thick BM (3.3% Bitumen) - 2108850.00
11 75 mm thick DBM (3.3% Bitumen) - 3104770.00
12 30 mm thick Bituminous Concrete with 5.2% Bitumen (3.75 m wide) - 1774500.00
13 50 mm thick DBM (4.5% Bitumen) - 2487600.00
14 75 mm thick BM (4.5% Bitumen) - 3672890.00
15 Construction of Cement Concrete Drain (One side in M-20 grade cement concrete) - 5358000.00

Pipe Culverts Stage-I Rates 2022-23 (With NP3 Pipes)

Sr No Details Culverts 7.5 m width (Rs.) Culverts 10.0 m width (Rs.)
1 800 mm Single row 397000 415900
2 800 mm Double row 510400 558200
3 800 mm Three row 629000 706600
4 900 mm Single row 424600 451300
5 900 mm Double row 560700 611900
6 900 mm Three row 693000 769800
7 1000 mm Single row 468500 496300
8 1000 mm Double row 615400 672200
9 1000 mm Three row 710700 847500
10 1200 mm Single row 564200 600600
11 1200 mm Double row 734600 823100
12 1200 mm Three row 936000 1045500
Sr No Item of Work Rates Proposed 2022-23 (Rs.) Unit
1 Causeway / Hard Passage (7.50 m wide) - Without vents 28700 Per Meter
Causeway / Hard Passage (7.50 m wide) - With Pipes 26300 Per Meter

Notes

  • Length of Causeway / Hard Passage should be measured as length of A.H.F.L (Afflux High Flood Level).
  • Add 15% for B.C soil area.
  • Work out proportional rate for causeway / hard passages having width more or less than 7.50 meter.

Minor Bridges or Slab Drains Stage-I Rates 2022-23 (7.50 m wide & upto 5.00 m height)

Sr No Details Rate (Rs.) Unit
(i) With open foundation 54617 Per Meter
(ii) With raft foundation 63857 Per Meter
(iii) With Box cells 500125 Per Meter
(iv) Non Submersible approaches 26180 Per Meter
(v) Submersible approaches 45629 Per Meter

Additional Notes

  • Work out proportionate rates for bridges wider or lesser than 7.50 meter and above 5.00 meter height.
  • For major bridges and special/state art bridges, actual detailed estimate to be prepared.

General Notes

  • Ghat area / Sugarcane area – Add 15%
  • Tribal area – Add 10%
  • Approved Action Plan (Non-Tribal) – Add 10%
  • Gadchiroli District – Extra 20%
  • Corporation area – Add 5%
  • Average lead of 30 km is considered for road work.
  • Bitumen lead is considered from refinery to plant site.
Sr No Item of Work Rates Proposed 2022-23 (Rs.) Unit
1 Causeway / Hard Passage (7.50 m wide) - Without vents 28700 Per Meter
Causeway / Hard Passage (7.50 m wide) - With Pipes 26300 Per Meter

Notes

  • Length of Causeway / Hard Passage should be measured as length of A.H.F.L (Afflux High Flood Level).
  • Add 15% for B.C. soil area.
  • Work out proportional rate for causeway / hard passages having width more or less than 7.50 meters.

Minor Bridges or Slab Drains Stage-I Rates 2022-23 (7.50 m wide & upto 5.00 m height)

Sr No Details Rate (Rs.) Unit
(i) With open foundation 54617.00 Per Meter
(ii) With raft foundation 63857.00 Per Meter
(iii) With Box cells 500125.00 Per Meter
(iv) Non-Submersible approaches 26180.00 Per Meter
(v) Submersible approaches 45629.00 Per Meter

Additional Notes

  • Work out proportionate rates for bridges wider or lesser in width than 7.50 meter and above 5.00 meter height.
  • For major bridges and special / State-of-Art bridges, actual detailed estimate should be prepared.

Buildings – Rates Proposed (Stage-I, 2022-23)

Sr No Item of Work Rate Proposed 2022-23 (Rs.) Unit
1 I.T.I Buildings, Administrative Buildings and other similar structures – Ground Floor 30000.00 Per Sqm
I.T.I Buildings, Administrative Buildings and other similar structures – First Floor 24450.00 Per Sqm
2 Hostel, Courts, Urban Hospital and other similar Buildings – Ground Floor 30100.00 Per Sqm
Hostel, Courts, Urban Hospital and other similar Buildings – First Floor 25250.00 Per Sqm
3 Rural Hospital and other similar Buildings – Ground Floor 24700.00 Per Sqm
4 Residential Quarters (Type III, IV & V) – Ground Floor 25000.00 Per Sqm
Residential Quarters (Type III, IV & V) – First Floor 21200.00 Per Sqm
5 Residential Quarters (Type II, IV & V) – Ground Floor 28800.00 Per Sqm
Residential Quarters (Type II, IV & V) – First Floor 23450.00 Per Sqm
6 Bungalows of Hon’ble Judges and other similar Buildings – Ground Floor 29000.00 Per Sqm
Bungalows of Hon’ble Judges and other similar Buildings – First Floor 24000.00 Per Sqm

Notes

  1. The above rates shall be increased by 1% for every floor above first floor.
  2. The above rates are for preparing Stage-I estimates for Buildings and these rates shall not be used for any type of valuation purpose.
  3. The above rates are basic rates and these shall be increased by percentage specified in the State Schedule of Rates for tribal area, inaccessible area, Municipal Council and Corporation area, Factories, Prison and Naxalite area for Gadchiroli District.
  4. The provision like contingencies, Electrification other than Internal & External, External Water supply and sanitary, Garden and Landscaping, Green Building and other provisions appropriate percentage shall be separately added.
  5. The above rates are for R.C.C. framed structure and the rates shall be increased or decreased suitably depending on actual site conditions where raft foundation or load bearing structure is provided, and reasons for same shall be furnished.