Method Statement for Formwork & Shuttering Works
1.0 Revision Status
| Revision Number | Date | Originator | Reviewed | Approved | Description of Re-submittal |
|---|---|---|---|---|---|
2.0 Scope & Objectives
- This Method Statement details the procedure for Formwork/Shuttering required to contain fresh/plastic concrete and mold it into the specified shapes, levels, and desired surface finishes[cite: 1].
- The contractor shall design and prepare structural formwork drawings supported by calculations, taking into account all static, dynamic, and hydrostatic construction loads[cite: 1].
3.0 Reference Standards
- Project Technical Specifications[cite: 1]
- Approved Civil & Structural Drawings[cite: 1]
- IS 6461 (Part 5): 1972 – Glossary of terms relating to cement concrete: Part 5 Formwork for concrete[cite: 1].
- IS 303: 1989 – Plywood for General Purposes – Specification[cite: 1].
- IS 4014 (Part 1): 1967 – Code of Practice for Steel Tubular Scaffolding[cite: 1].
- IS 8989: 1978 – Safety Code for Erection of Concrete Framed Structures[cite: 1].
4.0 Definitions & Abbreviations
| MS | Method Statement[cite: 1] |
| QCP | Quality Control Procedure[cite: 1] |
| ITP | Inspection & Test Plan[cite: 1] |
5.0 Health & Safety Hazards
Specific safety measures must be followed strictly as applicable during field execution[cite: 1]. All overarching safety protocols are covered separately in the Project HSE Plan[cite: 1].
5.1 Formwork and Falsework (F&F) Terminology
- Columns: External horizontal framing collar encircling column forms against bulging[cite: 1].
- Slipform: Structural frame straddling inner and outer formwork faces[cite: 1].
- Horizontal: Two-way structural ties engineered to restrict the effective slenderness ratio of vertical props[cite: 1].
- Diagonal: Inclined framing elements engineered to transfer wind and lateral forces directly through props[cite: 1].
6.0 Roles & Responsibilities
6.1 Project Engineer
- Verify that formwork operations strictly adhere to contract specifications, structural drawings, and approved design calculations[cite: 1].
- Ensure activities progress according to the baseline schedule and confirm all necessary formwork systems and staging materials are available in good condition[cite: 1].
- Coordinate directly with the Client, Consultant, Project Manager, Site Engineer, Safety Engineer, and Surveyors for safe execution[cite: 1].
- Enforce quality control standards and safety protocols in coordination with QA/QC and HSE teams[cite: 1].
6.2 Site Engineer
- Direct daily shuttering operations in accordance with approved shop drawings and project specifications[cite: 1].
- Provide detailed instruction and assign specific operational responsibilities to the execution crew[cite: 1].
- Track daily productivity, compare against project targets, and submit updates to the Project Engineer / Project Manager[cite: 1].
- Coordinate with Safety Engineers to maintain safe field practices during erection and dismantling[cite: 1].
- Coordinate with QA/QC Engineers to arrange timely field inspections for completed shuttering elements[cite: 1].
- Cross-check daily site production against reports provided by Foremen[cite: 1].
- Distribute updated structural drawings and revisions immediately to the field execution team[cite: 1].
- Work with Surveyors to verify levels, verticality, plumbness, and line alignment before concrete placement[cite: 1].
6.3 QA/QC Engineer
- Ensure all shuttering materials, release agents, and assembly procedures meet quality requirements[cite: 1].
- Perform preliminary field inspections on finished formwork before issuing official requests for client/consultant inspection[cite: 1].
- Maintain structured inspection records, pre-pour checklists, and test documentation for official records[cite: 1].
6.4 Safety Engineer
- Enforce project safety procedures in line with the HSE plan and conduct relevant site safety briefings[cite: 1].
- Monitor working platforms, staging systems, edge protection, and access ladders to prevent accidents[cite: 1].
- Perform regular field safety audits and report hazards or incidents immediately to project management[cite: 1].
- Ensure work areas are kept clean, tidy, and free of trip hazards[cite: 1].
6.5 Foreman
- Distribute daily labor, tools, shuttering plates, and staging equipment in coordination with the Site Engineer[cite: 1].
- Submit daily progress reports and coordinate upcoming resource requirements with the Site Engineer[cite: 1].
- Assist the surveyor during layout setting out, line marking, and level checks[cite: 1].
- Enforce safety guidelines and quality parameters directly on the field workforce[cite: 1].
- Report unexpected site conditions, material damage, or safety concerns immediately[cite: 1].
6.6 Surveyor
- Establish project benchmarks from approved reference points and provide line layout, axis grid, and level markings[cite: 1].
- Perform routine check measurements during formwork assembly to maintain design tolerances[cite: 1].
- Record line alignment and soffit elevation metrics, reporting deviations to the Site Engineer[cite: 1].
7.0 Construction Procedure & Work Methodology
- Preparatory Works: Inspect, clean, and grade steel form panels or plywood sheets prior to deployment[cite: 1].
- Layout & Dimensional Checks: Verify overall layout line alignment, vertical elevation, and grid intersections against approved structural construction drawings[cite: 1].
- Erection & Structural Integrity: Assemble formwork centering and shuttering as detailed in specifications prior to concrete placement to confine and mold wet concrete[cite: 1]:
- Forms must offer sufficient strength to safely carry hydrostatic concrete loads, dynamic placement impact, and temporary construction live loads[cite: 1].
- System stiffness must prevent surface deflection or joint displacement under full concrete weight[cite: 1].
- Design systems to enable clean, scientific striking without jarring or damaging cured concrete surfaces[cite: 1].
- Ensure adequate working space and clear access for concrete placement and compaction equipment[cite: 1].
- Joint Sealing & Fixation: Secure shuttering joints, corner angles, and panel connections tightly to prevent cement slurry leakage during vibration[cite: 1].
- Release Agent Application: Apply an even coating of approved form release oil or stripping oil to interior form contact faces to prevent concrete adhesion[cite: 1].
- Bracing Systems: Install adequate longitudinal, lateral, and vertical bracing to stabilize systems against lateral pressures from fresh concrete placement[cite: 1].
- Controlled Stripping: Apply form release agents systematically to facilitate safe, clean dismantling during formwork removal[cite: 1].
8.0 Material Requirements
All materials utilized must comply with project structural requirements and relevant code specifications[cite: 1]:
- Timber / Wood framing elements[cite: 1]
- Composite timber and hybrid wooden framing components[cite: 1]
- Shuttering Plywood (conforming to IS 303)[cite: 1]
- Aluminum formwork panels and beams[cite: 1]
- Steel shuttering plates and tubular staging elements[cite: 1]
- Engineered plastic formwork systems[cite: 1]
- Chemical form release agents and stripping oils[cite: 1]
9.0 Equipment Requirements
10.0 Health & Safety Provisions
- Prioritize site safety throughout formwork assembly, concrete placement, and stripping[cite: 1].
- Where formwork or falsework is erected at heights, install standard guardrails, perimeter barriers, safety netting, advance warning signs, and hazard warning tape around the perimeter[cite: 1].
- Implement controlled safety measures during formwork stripping, including restricted exclusion zones, overhead protection, and PPE usage[cite: 1].
11.0 Quality Control Approvals
The following quality control documentation must be formally submitted and approved prior to starting formwork operations[cite: 1]:
- Quality Control Procedure (QCP) for Formwork Works[cite: 1]
- Inspection & Test Plan (ITP) for Formwork Works[cite: 1]
- Project Field Quality Plan[cite: 1]
- Execution & Pre-Pour Checklists for Formwork[cite: 1]
12.0 Supporting Documentation
This Method Statement must be implemented alongside the following documents[cite: 1]:
- Contract Specifications and Structural Construction Drawings[cite: 1]
- Quality Control Procedure (QCP) for Formwork[cite: 1]
- Inspection & Test Plan (ITP) for Formwork[cite: 1]
- Method Statement (MS) for Formwork[cite: 1]
- Project Quality Plan[cite: 1]
- Project HSE Plan[cite: 1]
13.0 Distribution List
Copies distributed for implementation, compliance, and record maintenance[cite: 1]:
- Management Representative[cite: 1]
- Project Manager[cite: 1]
- Project Engineer[cite: 1]
- Site Engineer[cite: 1]
- HSE Engineer[cite: 1]
- QA/QC Engineer[cite: 1]