Rigid Pavement Construction Flowchart with IRC & MoRTH References
flowchart TD
A1([Start
Ref: IRC:15 Intro]) A2["Subgrade Preparation
• Achieve 97% MDD
• Remove soft pockets
Ref: MoRTH 305, IRC:15 Cl. 5.1"] A3["DLC Placement
• 10–20 MPa
• Min 100 mm thick
• Compacted with roller
Ref: MoRTH 601, IRC:SP:62"] A4["DLC Curing
• 7 days minimum
Ref: IRC:SP:62 Cl. 7"] A5["Surface Cleaning
• Remove dust & laitance
Ref: MoRTH 602.4.1"] A6["Polyethylene Sheet Laying
• 125 micron
• Joints overlapped 300 mm
Ref: MoRTH 602.4.2"] A7["Dowels & Tie Bars Placement
• Epoxy-coated
• Dowel tolerance: ±5 mm
• Tie bars as per IRC:58 Table 10
Ref: IRC:58 Cl. 10"] A8["Side Forms / Slipform Setup
• Level tolerance ±3 mm
Ref: MoRTH 602.5"] A9["Concrete Batching & Mixing
• w/c ratio per IS 10262
• Use IS 383 aggregates
Ref: MoRTH 602.6, IS 9103"] A10["Concrete Transport
• No segregation
• Place within 30 min
Ref: MoRTH 602.7"] A11["Concrete Placement
• No vibration on dowels
• Spread uniformly
Ref: MoRTH 602.8"] A12["Compaction with Vibrators
• Internal & surface vibrator
• Avoid over-vibration
Ref: IRC:15 Cl. 8.3"] A13["Surface Finishing
• Texturing with burlap or broom
Ref: MoRTH 602.9"] A14["Alignment & Level Checks
• Straightedge check 3 m
• Max 3 mm deviation
Ref: IRC:15 Cl. 10"] A15["Joint Cutting (Grooving)
• 1/3 slab depth
• Saw-cut within 6–24 hrs
Ref: IRC:58 Cl. 11.3"] A16["Joint Sealing
• Sealant Type: Polysulphide
• Reservoir cleaning required
Ref: IRC:57 & MoRTH 602.13"] A17["Curing of PQC
• 14 Days minimum
• White curing compound allowed
Ref: IRC:15 Cl. 11"] A18["Opening to Traffic
• Strength >= 30 MPa
• Min 28 days unless permitted
Ref: IRC:15 Cl. 12"] A19([End]) A1 --> A2 --> A3 --> A4 --> A5 --> A6 --> A7 --> A8 --> A9 --> A10 A10 --> A11 --> A12 --> A13 --> A14 --> A15 --> A16 --> A17 --> A18 --> A19
Ref: IRC:15 Intro]) A2["Subgrade Preparation
• Achieve 97% MDD
• Remove soft pockets
Ref: MoRTH 305, IRC:15 Cl. 5.1"] A3["DLC Placement
• 10–20 MPa
• Min 100 mm thick
• Compacted with roller
Ref: MoRTH 601, IRC:SP:62"] A4["DLC Curing
• 7 days minimum
Ref: IRC:SP:62 Cl. 7"] A5["Surface Cleaning
• Remove dust & laitance
Ref: MoRTH 602.4.1"] A6["Polyethylene Sheet Laying
• 125 micron
• Joints overlapped 300 mm
Ref: MoRTH 602.4.2"] A7["Dowels & Tie Bars Placement
• Epoxy-coated
• Dowel tolerance: ±5 mm
• Tie bars as per IRC:58 Table 10
Ref: IRC:58 Cl. 10"] A8["Side Forms / Slipform Setup
• Level tolerance ±3 mm
Ref: MoRTH 602.5"] A9["Concrete Batching & Mixing
• w/c ratio per IS 10262
• Use IS 383 aggregates
Ref: MoRTH 602.6, IS 9103"] A10["Concrete Transport
• No segregation
• Place within 30 min
Ref: MoRTH 602.7"] A11["Concrete Placement
• No vibration on dowels
• Spread uniformly
Ref: MoRTH 602.8"] A12["Compaction with Vibrators
• Internal & surface vibrator
• Avoid over-vibration
Ref: IRC:15 Cl. 8.3"] A13["Surface Finishing
• Texturing with burlap or broom
Ref: MoRTH 602.9"] A14["Alignment & Level Checks
• Straightedge check 3 m
• Max 3 mm deviation
Ref: IRC:15 Cl. 10"] A15["Joint Cutting (Grooving)
• 1/3 slab depth
• Saw-cut within 6–24 hrs
Ref: IRC:58 Cl. 11.3"] A16["Joint Sealing
• Sealant Type: Polysulphide
• Reservoir cleaning required
Ref: IRC:57 & MoRTH 602.13"] A17["Curing of PQC
• 14 Days minimum
• White curing compound allowed
Ref: IRC:15 Cl. 11"] A18["Opening to Traffic
• Strength >= 30 MPa
• Min 28 days unless permitted
Ref: IRC:15 Cl. 12"] A19([End]) A1 --> A2 --> A3 --> A4 --> A5 --> A6 --> A7 --> A8 --> A9 --> A10 A10 --> A11 --> A12 --> A13 --> A14 --> A15 --> A16 --> A17 --> A18 --> A19
IRC References for Pavement QC Tests
| Test Category | Specific Test | Primary IRC Reference | Notes / Related Standards |
|---|---|---|---|
| 1. Soil / Subgrade Tests | Field Density Test (Sand Cone / Nuclear Gauge) | IRC:SP:20-2002, IRC:37-2018 | IS:2720 (Part 28); 95–100% Proctor density |
| CBR Test (California Bearing Ratio) | IRC:37-2018, IRC:SP:72-2015 | IS:2720 (Part 16); soaked CBR for design | |
| Atterberg Limits | IRC:SP:20-2002, IRC:37-2018 | IS:2720 (Part 5); plasticity index control | |
| Proctor Test (OMC & MDD) | IRC:37-2018, IRC:SP:72-2015 | IS:2720 (Part 8); Modified Proctor | |
| 2. Base & Sub-Base Layer Tests | Gradation Test (Sieve Analysis) | IRC:SP:11-1984, IRC:109-2015 | IS:2386 (Part 1) |
| Aggregate Crushing Value (ACV) | IRC:SP:11-1984, IRC:37-2018 | Max 30%; IS:2386 (Part 4) | |
| Los Angeles Abrasion (LAA) | IRC:SP:11-1984, IRC:109-2015 | Max 40%; IS:2386 (Part 4) | |
| Field Density Test | IRC:SP:11-1984 | IS:2720 (Part 28) | |
| Plate Load Test | IRC:SP:11-1984 | Bearing capacity & modulus | |
| 3. Asphalt (Flexible Pavement) QC Tests | Asphalt Content (Extraction Test) | IRC:SP:11-1984 | IS:2720 (Part 19) |
| Marshall Stability & Flow Test | IRC:SP:11-1984, IRC:111-2009 | Min 9 kN stability | |
| Core Cutting & Thickness Check | IRC:SP:11-1984, IRC:29-2009 | Tolerance ±5 mm | |
| Density / Compaction Test | IRC:SP:11-1984 | 95–98% of lab density | |
| Temperature Monitoring | IRC:SP:11-1984, IRC:111-2009 | Mix 150–165°C, laying >100°C | |
| Air Voids & VMA / VFA Analysis | IRC:SP:11-1984, IRC:37-2018 | Air voids 3–6%, VMA >14% | |
| 4. Concrete (Rigid Pavement) QC Tests | Slump Test | IRC:15-2011, IRC:SP:62-2004 | 25–50 mm; IS:1199 |
| Compressive Strength (7-day & 28-day) | IRC:15-2011, IRC:44-2017 | Min 30 MPa (M40); IS:516 | |
| Flexural Strength (Modulus of Rupture) | IRC:15-2011, IRC:58-2015 | Min 4.5 MPa; IS:516 | |
| Air Content Test | IRC:15-2011 | 4–6%; IS:1196 | |
| Concrete Temperature Test | IRC:15-2011 | Max 32°C at placement | |
| Core Thickness & Strength Check | IRC:15-2011, IRC:SP:83-2008 | Tolerance ±5 mm | |
| 5. Surface Quality Tests | Benkelman Beam Deflection (BBD) | IRC:81-1997 | Structural evaluation |
| IRI (International Roughness Index) | IRC:SP:16-2004 | <2.5 m/km acceptable | |
| Skid Resistance Test | IRC:SP:11-1984 | British Pendulum Number ≥45 | |
| Texture Depth (Sand Patch Method) | IRC:SP:11-1984 | Min 0.6–1.0 mm |
0 Comments
If you have any doubts, suggestions , corrections etc. let me know